# Little.R, 29 Sep 19 | |
# | |
# Data from: | |
# Schedule Estimation and Uncertainty Surrounding the Cone of Uncertainty | |
# Todd Little | |
# | |
# Example from: | |
# Evidence-based Software Engineering: based on the publicly available data | |
# Derek M. Jones | |
# | |
# TAG project_estimate estimate_initial | |
source("ESEUR_config.r") | |
library("plyr") | |
pal_col=rainbow(2) | |
# Project Code,Week End Date,Target RelDate,Env,Plan,Dev,Stab,Mob,Adj Week,Est EndDate,First Est,Actual Release,Start Date,X,Absolute Ratio,Relative Ratio,Update,Absolute ratio without factor 2,,Eind project,Oppervlakte,Counter,Som oppervlakte,EQF all,EQF end,Eind project factor 2,Oppervlakte factor 2,Counter factor 2,Som oppervlakte factor 2,EQF all factor 2,EQF end factor 2 | |
# 1,12/01/00,03/01/01,C,C,I,,,12/01/00,03/01/01,03/01/01,08/22/01,12/01/00,0.00,0.6770156819,2.95,1,0.33851,,0,0.0085951791,1,0,4235.7284514877,0,0,0.0176034663,1,0,#DIV/0!,0 | |
est=read.csv(paste0(ESEUR_dir, "projects/Little06.csv.xz"), as.is=TRUE) | |
est$Week.End.Date=as.Date(est$Week.End.Date, format="%m/%d/%y") | |
est$Target.RelDate=as.Date(est$Target.RelDate, format="%m/%d/%y") | |
est$Adj.Week=as.Date(est$Adj.Week, format="%m/%d/%y") | |
est$Est.EndDate=as.Date(est$Est.EndDate, format="%m/%d/%y") | |
est$First.Est=as.Date(est$First.Est, format="%m/%d/%y") | |
est$Actual.Release=as.Date(est$Actual.Release, format="%m/%d/%y") | |
est$Start.Date=as.Date(est$Start.Date, format="%m/%d/%y") | |
est$est_duration=est$First.Est-est$Start.Date | |
mk_target_unique=function(df) | |
{ | |
# The same Target release date might be estimated again after a change of date, | |
# so duplicated cannot be used. rle only works with atomic types | |
t=cumsum(c(1, head(rle(as.integer(df$Target.RelDate))$lengths, n=-1))) | |
return(df[t, ]) | |
} | |
target_summary=function(df) | |
{ | |
return(data.frame(est_duration=df$est_duration[1], num_reest=nrow(df))) | |
} | |
u_est=ddply(est, .(Project.Code), mk_target_unique) | |
t_sum=ddply(u_est, .(Project.Code), target_summary) | |
plot(t_sum$est_duration,t_sum$num_reest, col=pal_col[2], | |
xlab="Initial estimated duration (days)", ylab="Number of estimates\n") | |
lines(loess.smooth(t_sum$est_duration, t_sum$num_reest, span=0.5, family="gaussian"), col=pal_col[1]) | |