4.0.4 - April 1, 2025

  • New Features
    • Addition of new policy levers to represent repeal of current policy: Differentiates vehicle standards into national and subnational levers and allows for repeal of current policy in either jurisdiction, new options for increased process emissions in policy scenarios, non-BAU distributed solar capacity, non-BAU industrial CCS, non-BAU hydrogen production pathway shifting
    • Extends the policy selection slider bars to encompass negative values for several preexisting policy levers in order to represent repeal of current policies and adds some policy options to the web app that were previously visible only in Vensim (e.g. use non-BAU coal retirement schedule)
    • Adds a new lever for subsidies for production of grid batteries
    • Added additional options to specify BAU and policy thermal fuels subsidies by sector
    • New adjustment mechanism to calculate time-adjusted capacity factors for plants coming online in the modeled timestep
  • Bug Fixes
    • Fixes bugs in electricity export cash flow accounting, electricity supplier cost recovery, electricity dispatch
    • Adds missing cash flow accounting for grid battery subsidies
    • Fixes accounting of subsidies per unit electricity produced based on when new capacity was added and the subsidy duration
    • Avoids potential divide by zero error in calculations for green hydrogen electricity demand
    • Fixes double counting of CCS transportation and storage costs in revenue accounting
    • Fixes incorrect calculations for emissions from blue hydrogen production
    • Fixes calculations for BAU carbon tax rate on exported products and cash flows from BAU carbon tax on process emissions
    • Limits the positive cost RPS qualifying dispatch mechanism once the RPS requirement is reached and improves the calculation of RPS requirements
    • Updates weighted average variable subsidies to be correctly calculated based on last year capacity built
    • Resolves errors in equality checks for revenue balancing in electricity sector nonenergy revenues and energy supplier revenues
    • Removes macroeconomic feedback effects on passenger transportation demand and building service demand
    • Incorporates CES alternative compliance payment costs into cash flows and removes anticipated market revenues in CES ongoing costs
    • Removes electricity exports from the calculation of capacity needed for reliability
    • Sets capacity market payments for residual reliability to be made to only the reliability electricity source subscript
    • Removes subsidies from the change in energy industry revenues used in IO calculations
  • Data updates
    • Updates calculations for BAU vehicle tax credits
    • Fixes to BAU clean electricity tax credit calculations and CCS tax credit calculations
    • Updates all policy implementation schedules to start in 2025
    • Updates output currency year to 2024
    • Recalibrates the share of costs that to be covered to be considered profitable and capacity supply curves for the electricity sector
    • Updates BAU planned capacity additions to use latest EIA data on plants that have received regulatory approval
    • Updates natural gas prices based on latest gas futures data
    • Updates government revenue accounting settings to use deficit spending for all government cash flow types
    • Updates to capacity factors for new onshore wind
    • Changes the repayment period for capacity market changes to 3 years
    • Updates transmission construction costs to exclude spur line costs, which are captured separately

eps-4.0.3-us

12 Dec 20:46

Choose a tag to compare

4.0.3 - December 12, 2024

  • New Features
    • Addition of a new industrial feedstock shifting policy lever
    • New improved tracking of dedicated clean power plants built for green hydrogen production
    • New policy lever for non-BAU zero-emission vehicle requirements at the subregional level (e.g. at the US state level)
    • Addition of new structure to support the breaking out of power plants' own use of electricity
    • Grid storage is now integrated with the capacity additions mechanism
    • New control lever for how to integrate capacity market revenue into cash flows
    • Addition of a minimum distributed solar capacity lever
    • New policy lever to ban CCS retrofits by power plant type
    • Addition of a smoothing time to smooth power plant decommissioning costs
    • Replace thermochemical water splitting hydrogen production pathway with partial oxidation of hydrocarbons option
    • Improves the representation of electricity cash flows, for example smoothing energy market revenues and wholesale energy market costs and combining least-cost and guaranteed dispatch into a single energy market
  • Bug Fixes
    • Correct error in process emissions abatement potential for oil and gas CH4
    • Correct double counting of a portion of emissions from hydrogen production
    • Corrects bugs in the calculation of incremental capacity and dispatch from the clean electricity standard policy
    • Correct how the percentage fuel use reductions for electricity are applied to the industrial electrification policy lever
    • Add missing MAX function to two different variables to prevent mismatches between policy and BAU versions of EPS outputs
    • Move emissions from ethanol production from the chemicals subsector into refining
    • Prevent least cost dispatch from being negative in certain cases
    • Allows the ZEV standard to now be applied to non-road vehicle types
    • Fixes to revenue and deployment calculations for hybrid power plants
  • Data updates
    • Update historical process emissions data based on EPA's Greenhouse Gas Inventory 1990-2022
    • Update pollutant emissions intensities to use the latest EPA National Emissions Inventory for non-GHGs and EPA GHG Inventory data for N2O emissions from mobile combustion
    • Update hydrogen prices for the electricity sector to assume blue hydrogen
    • Update short-term natural gas prices to use latest gas futures estimates
    • No longer estimate the portion of buildings sector fuel demand used for district heating and instead represent all fuel use and emissions within the buildings sector

eps-4.0.2-us

09 Sep 15:53

Choose a tag to compare

4.0.2 - September 9, 2024

  • New Features
    • Subscript fuel tax/subsidy lever by sector
    • Update cost-effective capacity additions structure to use expected $/MWh profits rather than a multiplier representing the ratio of revenues to costs
    • Update calculation methodology for electricity rates by collecting capacity market revenues over ten years and collecting all other non-amortized costs on an annual basis
  • Bug Fixes
    • Implement one year delay on industry pass through expenses to align calculations and avoid potential for oscillating outputs
    • Correct equation for change in decommissiong costs
    • Revise calculation of changes in energy demand for energy pipelines and processing to be based on energy consumption rather than energy production
    • Correct BAU values for the production tax credit to use correct currency conversion factor
    • Set hydrogen fuel costs to not vary based on changes in production costs, since our input data already accounts for projected changes in production pathways
  • Data updates
    • Update to ATB 2024 and extend input data to cover all historical years rather than just the start year
    • Update global wind, solar, and battery deployment (used in endogenous learning calculations) to use latest projections
    • Additional calibration of historical year electricity generation

eps-4.0.1-us

13 Aug 21:24

Choose a tag to compare

4.0.1 - August 14, 2024

  • New Features
    • Enable policy scenarios to set different values for the RPS Alternative Compliance Payment
    • Added structure to address the duration of subsidies in dispatch calculations. Previously, we correctly amortized subsidies for deciding what/how much new capacity to build, but did not include the duration in the estimation of dispatch costs in the future. This primarily affects CCUS units receiving 45Q tax credits in the US
  • Bug Fixes
    • Address a bug with calculating marginal dispatch costs by hour
    • Update to handling of coal retirements
    • Update to remove double counting of some capacity built for clean dispatchable reliability
    • Correct methodological error in calculation of load with transmission and distribution losses
    • Correct methodological error in how a ban on CCUS retrofits can be applied
    • Correct methodological error in RPS dispatch of certain resources that could lead to overgeneration
  • Data Updates
    • Update handling of hydro dispatch
    • Data correction in file indst/PERAC for methane abatement potential
    • Data correction in file indst/BIFUbC for LPG energy demand
    • Data correction in file elec/BPSpUGBDC for phaseout of battery storage tax credits
    • Updated curve parameters for clean dispatchable supply
    • Updated the NDC scenario to start implementing policies in 2025, and modify the enhanced rock weathering setting

eps-4.0.0.1-us

08 Jul 18:26

Choose a tag to compare

4.0.0.1 - July 8, 2024

  • Data Updates
  • Data correction in file endo/learn/FoTOMRAEL

eps-4.0.0-us

04 Jul 00:25

Choose a tag to compare

4.0.0 - July 5, 2024

  • New Features
    • Redesigned electricity module, including hourly demand and dispatch for six time slices. This allows for both profitability- and reliability-based capacity expansion mechanisms; endogenous cost-driven retirements and retrofits; endogenous deployment, charging, and discharging of electricity storage; endogenous deployment of transmission and distribution; and a new bottom-up calculation of electricity rates.
    • Seven new power plant types: hard coal with CCS, natural gas combined cycle with CCS, biomass with CCS, lignite with CCS, small modular reactors, hydrogen combustion turbines, and hydrogen combined cycle plants
    • Added new hydrogen production pathways for electrolysis with dedicated clean electricity and steam methane reforming with CCS
    • Disaggregated industrial fuel consumption by industry into eight different industrial processes
    • Diaggregated industry CCS costs by industry
    • Added CCS transportation and storage costs to CCS cash flows
    • Updated logit function for transportation vehicle purchasing decisions to better reflect deployment of different vehicle technologies
    • The BAU Clean Electricity Standard is now tracked by subregion (in the US model, at the state-level)
    • Added BAU CCS subsidies to the model
    • Added the ability to track spending due to BAU distributed solar subsidies
    • Added the ability for BAU data to have changes in domestic content share by ISIC code in future years rather than using static input data
    • Endogenous learning now functions based on the change from last year rather than the change from the start year. This allows users to switch over from historical data to endogenous learning in any year of the model run, rather than limiting users to only one year's worth of historical data.
    • Added a control lever to enable/disable RPS/CES foresight
    • Added control lever to set which industries and vehicle types are subject to the carbon tax.
    • Added control lever to set which industries and are covered by a carbon tax border adjustment.
    • Redesigned structure for calculating changes in battery prices and impact on changes in vehicle prices.
  • New Policies
    • Levers for industrial fuel shifting are now split into separate electrification and hydrogen fuel shifting policies, which can both be separately set for different industrial processes
    • Reintroduced the EV charger lever, which is now tied to the model's shadow cost for range anxiety
    • Vehicle subsidies are now subscripted by vehicle technology
    • Added a policy lever to subject a non-BAU set of vehicles to the Low Carbon Fuel Standard. The non-BAU option in the web app applies the standard to only aviation to represent sustainable aviation fuels
    • Subsidies per unit capacity or per unit electricity supplied from grid batteries
    • Percent change in share of EVs used for grid balancing
    • Additional subsidies for CCS
    • Subsidies for the production of EV batteries
    • Added an enhanced rock weathering policy lever to the geoengineering sector
  • Bug Fixes
    • Quantization fix to avoid small policy effects in BAU case for Change in Energy Export Revenue graph in some cases
    • Fix to tracking of industry CCS for process vs. energy-related emissions
    • Fix that prevents the variable for BAU max new elec output still buildable falling below 0 in rare use cases
    • Corrected double counting of petroleum products in primary energy graphs
  • Data Updates
    • Updated BAU to reflect components of the Inflation Reduction Act and latest EPA rules (see documentation included in model download folder)
    • Updated to the Energy Information Administration's Annual Energy Outlook 2023 Reference Scenario
    • Updated to use the National Renewable Energy Laboratory's Annual Technology Baseline 2023
    • Updated to use updated PRIMAP database for process CO2 emissions
    • Updated short-term natural gas prices to reflect futures prices
    • Updated BAU methane emissions from the oil and gas sector to reflect latest Environmental Protection Agency standards
    • Updated NDC Scenario with updated policy assumptions
    • Updated passenger light-duty vehicle fuel economy to reflect differences in tested and onroad fuel economy reported by EIA
    • Updated passenger light-duty vehicle lifetime
    • Updated onroad vehicle prices with data from the International Council on Clean Transportation
    • Updated LULUCF emissions trajectory based on trends in the latest Greenhouse Gas Inventory
    • Updated mitigation potential in the agriculture and LULUCF sectors based on recent research from the EPA
    • Updates to historical and projected global capacity of certain technologies used in endogenous learning calculations
    • Updated to use EPA's NEEDS database for planned power plant retirements (replacing EIA)
    • Other minor data updates
  • New Graphs
    • Cumulative CO2e emissions and reductions (including and excluding land use)
    • Various hourly dispatch graphs
    • Industry fuel use by industrial process (separate graphs for thermal fuels and electricity)
    • Direct emissions by building type and end use
    • Emissiosn by building type and end use (reallocated energy carriers)
    • Final energy graphs (by source and by sector)
    • Carbon captured by end use
    • Carbon tax revenue by source
    • Hydrogen production by pathway

eps-3.4.9-us

18 Apr 16:08

Choose a tag to compare

3.4.9 - April 4, 2023

  • Bug fix
    • Prevent double counting in increases in fuel use for certain use cases of the industrial fuel shifting policy

eps-3.4.8-us

06 Dec 19:47

Choose a tag to compare

3.4.8 - December 6, 2023

  • New Features
    • The Zero-Emission Vehicle Sales Standard can now be applied to nonroad vehicles in Vensim
  • Bug fix
    • Prevent rare Vensim error affecting total available capacity by source type caused by a missing MAX function in an electricity sector variable

eps-3.4.7-us

08 Jun 16:51

Choose a tag to compare

3.4.7 - June 8, 2023

  • Bug fix
    • Prevent rare Vensim error caused by negative ppriority values in ALLOCATE AVAILABLE function

eps-3.4.6-us

16 May 17:11

Choose a tag to compare

3.4.6 - May 16, 2023

  • Bug fix
    • Allow changes in capacity construction subsidies to affect electricity prices