OverAllocated Element
OverAllocated Element
9f8faa7d-0f6a-4822-99a0-aaf381af279b
13188306
03/14/2018
v=office.12
OverAllocated element
>= project-client-2007 || project-client-odc
medium

OverAllocated Element

For a Task, Overallocated indicates whether an assigned resource on a task has been assigned to more work on the task than can be done within the normal working capacity.

For a Resource, it indicates whether the resource is assigned more work on all tasks than can be done within the normal working capacity.

For an Assignment, it indicates whether a resource is assigned to more work on a specific task than can be done within the resource's normal working capacity.

<Overallocated>
  BooleanValue
</Overallocated>

Parent Elements

Task,Resource, Assignment

Occurrences

Minimum: 0

Maximum: 1

Text Value

A text value of type boolean is required.

Value

Description

0

False

1

True

See Also

Concepts

Task Elements and XML Structure

XML Schema for the Tasks Element

Resource Elements and XML Structure

XML Schema for the Resources Element

Assignment Elements and XML Structure

XML Schema for the Assignments Element