Analytics for tasks

Each task has an analytics section available from the left menu in the task view.

Lead and cycle time

Lead and cycle time

  • The lead time is the time between the task creation and the date of completion (task closed).
  • The cycle time is the time between the start date and the date of completion.
  • If the task is not closed the current time is used instead of the date of completion.
  • If the start date is not specified, the cycle time is not calculated.

Note: You can configure an automatic action to define the start date automatically when you move a task to the column of your choice.

Time spent into each column

Time spent into each column

  • This chart shows the total time spent into each column for the task.
  • The time spent is calculated until the task is closed.