Kubernetes 1.15

Links

Tracking docs

Guides

tl;dr

The 1.15 release cycle is proposed as follows:

  • Monday, April 08 - Release Cycle Begins
  • Tuesday, April 30th, EOD PST - Enhancements Freeze
  • Thursday, May 30th, EOD PST - Code Freeze
  • Tuesday, June 04 - Docs must be completed and reviewed
  • Monday, June 17th - Kubernetes 1.15.0 Released

What will we do differently this release?

  • To avoid releasing during KubeCon Shanghai (June 24-28) we will plan for an 11 week release cycle.

  • We have a new role on the release team - the emeritus lead.
    *The emeritus lead will be responsible for ensuring shadow selection happens and that release shadows are getting the most out of their participation in the release process

What are we continuing from the previous release

  • All Enhancements must have a KEP that is in an implementable state by enhancement freeze. If the enhanement does not have a KEP in an implementable state by enhancement freeze it will be removed from the milestone and will require an exception.

  • No code slush

Timeline

What Who WHEN WEEK
1.15 Release Cycle begins Release Lead Monday, April 08, 2019 Week 1
Schedule Finalized Release Lead Friday, April 12, 2019 Week 1
Release Team Finalized Release Team Leads Friday, April 12, 2019 Week 1
Start Enhancements Tracking Enhancements Lead Tuesday, April 16th, 2019 Week 2
1.15.0-alpha.1 released Branch Manager Lead Tuesday, April 16, 2019 Week 2
Start Release Notes Draft Release Notes Lead Tuesday, April 23, 2019 Week 3
Enhancements Freeze Enhancements Lead Tuesday, April 30th, 2019 Week 4
1.15.0-alpha.2 released Branch Manager Lead Monday, April 29, 2019 Week 4
1.15.0-alpha.3 releaed Branch Manager Lead Tuesday May 07, 2019 Week 5
1.15.0 branch cut Branch Manager Lead Tuesday, May 14th, 2019 Week 6
1.15.0-beta.0 released Branch Manager Lead Tuesday, May 14th, 2019 Week 6
1.15.0 release jobs created, 1.11.0 Jobs removed Test Infra Lead Thursday, May 16th, 2019 Week 6
Begin Burndown (MWF meetings) Release Lead Monday, May 27th, 2019 Week 8
1.15.0-beta.1 released Branch Manager Lead Tuesday, May 28th, 2019 Week 8
Docs Deadline - Open placeholder Prs Docs Lead Friday, May 31, 2019 Week 8
Code Freeze Test Infra Lead Thursday, May 30th, 2019 Week 8
Daily burndowns start Release Lead Monday, June 03, 2019 Week 9
Docs deadline - PRs ready for review Docs Lead Tuesday, June 04, 2019 Week 9
1.15.0-beta.2 released Branch Manager Lead Wednesday, June 05, 2019 Week 9
Docs Last Call Docs Lead Monday, June 10th, 2019 Week 10
Code Thaw Test Infra Lead Tuesday, June 11th. 2019 Week 10
1.15.0-rc.1 released Branch Manager Lead Tuesday, June 11th, 2019 Week 10
Cherry pick deadline Branch Manager Thursday, June 13th, 2019 Week 10
1.15.0 Released Branch Manager Lead Monday, June 17th, 2019 Week 11

Phases

Enhancements Freeze

All enhancements wishing to be included in 1.15 must have

  • A KEP in an implementable state
    • Including Testing Plans
    • Including Graduation Criteria
  • An open issue in the 1.15 Milestone

If your enhancement doesn't not meet these requirements it will be removed from the milestone and will require an exception.

Burndown

One week prior to Code Freeze, we increase the cadence of release team meetings to begin tracking work more closely. We call this Burndown, because at this point we have a list of outstanding issues and PRs, and are actively working to burn that list down. SIG representatives will be asked to attend if their SIG has specific outstanding issues that are blocking the release.

Join kubernetes-sig-release@ to get a calendar invite. This meeting may conflict with other community meetings. Please prioritize this meeting if a member of the release team asks you to attend.

The intent of these meetings is to:

  • Focus on fixing bugs, eliminating test flakes and general release stabilization.
  • Ensure docs and release notes are written and accurate.
  • Identify all enhancement going into the release, and make sure alpha, beta, GA is marked in enhancements repo.
  • Provide a one-stop view of release progress including relevant release metrics.

Code Freeze

All enhancements going into the release must be code-complete, including tests, and have docs PRs open by Thursday, May 30th, 2019.

The docs PRs don't have to be ready to merge, but it should be clear what the topic will be and who is responsible for writing it. This person will become the primary contact for the documentation lead. It’s incredibly important that documentation work gets completed as quickly as possible.

After this point, only release-blocking issues and PRs will be allowed in the milestone.

Code Thaw

One week prior to release, it is expected that all but a handful of outstanding PRs for kubernetes v1.16.0 have landed in the release-1.15 branch. Assuming the release team agrees, Code Freeze will be lifted, and we enter Code Thaw.

From this point forward, any PRs intended for v1.15 must be cherry picked to the release-1.15 branch.

Exceptions

Starting at Enhancements Freeze the release team will solicit and rule on exception requests for enhancements and test work that is unlikely to be done by Code Freeze. The exception approval is the responsibility of the SIG or SIGs labeled in the pull request. The release team may intervene or deny the request only if it poses a risk to release quality, or could negatively impact the overall timeline. Changes introduced at this point should be well-tested, well-understood, limited in architectural scope, and low risk. All of those factors should be considered in the approval process. Enhancements on an feature branch with documentation, test cases, and passing CI are more likely to be accepted.

Pruning

Enhancements that are partially implemented and/or lack sufficient tests may be considered for pruning beginning after Code Freeze, unless they've been granted an Exception.

The release team will work with SIGs and enhancements owners to evaluate each case, but for example, pruning could include actions such as:

  • Disabling the use of a new API or field
  • Switching the default value of a flag or field
  • Moving a new API or field behind an Alpha Enhancements gate
  • Reverting commits or deleting code

This should occur before 1.14.0-beta.1 is cut so we have time to gather signal on whether the system is stable in this state. These are considered drastic measures, so the release team will strive to coordinate at-risk work with SIGs before this time. The goal is to make code freeze, and overall project transparency, enforceable despite the lack of a consistently used feature branch process.

Docs

If an enhancement needs documentation, enter "Yes" in the enhancement tracking spreadsheet and add a link to the documentation PR. You can open documentation PRs in the kubernetes/website repository. If you have questions, the release documentation lead, or representatives from SIG-Docs will be happy to assist you.

For documentation PRs:

  • Open PRs against the dev-1.15 branch based off of the 1.15 release PR. The documentation workflow uses feature branches for release documentation, rather than basing from master. Be sure to open your PR against the release branch.