In sequence diagram, how force two message aligned at the same level #1699

Answered by The-Lum
shutaozhenzhen asked this question in Q&A
Discussion options

You must be logged in to vote

Hi @shutaozhenzhen,

Here is a proposal, using teoz:

@startuml
!pragma teoz true
main -> main: command1
slave1 -> slave1: command2
& slave2 -> slave2: command2
& slave3 -> slave3: command2
& slave4 -> slave4: command2
@enduml

See also:

Regards,
Th.