stuck jobs #5352

Open
@davidpanderson

Description

@davidpanderson

Reportedly, some VM jobs (and possibly others) get in a "stuck" state where they
don't make progress: no fraction done change, and little CPU usage.
These jobs will eventually be aborted when their elapsed time reaches the rsc_fpops_bound limit,
but this could take weeks or months depending on the limit.

Proposal: have the client try to figure out when a job is stuck.

ACTIVE_TASK new fields:
  double stuck_check_elapsed_time
  double stuck_check_fraction_done
  double stuck_check_cpu_time
  (initialize all to zero)

STUCK_CHECK_POLL_PERIOD = 3600

every STUCK_CHECK_POLL_PERIOD seconds
   for each active task atp
      if non_cpu_intensive: continue
      if sporadic: continue
      if atp->stuck_check_elapsed_time == 0
         atp->stuck_check_elapsed_time = atp->elapsed_time
         atp->stuck_check_fraction_done = atp->fraction_done
         atp->stuck_check_cpu_time = atp->current_cpu_time
         continue
      if atp->elapsed_time < atp->stuck_check_elapsed_time + STUCK_CHECK_POLL_PERIOD
        continue
     if atp->stuck_check_fraction_done == atp->fraction_done
        && (atp->current_cpu_time - atp->stuck_check_cpu_time < 10)
        (job is stuck - print warning)
     atp->stuck_check_elapsed_time = atp->elapsed_time
     atp->stuck_check_fraction_done = atp->fraction_done
     atp->stuck_check_cpu_time = atp->current_cpu_time

e.g. in the last hour of running, the fraction done hasn't changed,
and the incremental CPU time is < 10s.

At that point, the client could

  1. notify the user, suggesting that they abort the job
  2. abort the job

Let's do 1) for starters, to make sure that the logic is right,
then at some point do 2).

Metadata

Metadata

Assignees

No one assigned

    Type

    Projects

    Status

    In progress

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions