[PM] SOGS Progress #11

Closed
holanita opened this issue Sep 27, 2022 · 11 comments
Closed

[PM] SOGS Progress #11

holanita opened this issue Sep 27, 2022 · 11 comments
Assignees
Labels
pm project management
Milestone

Comments

@holanita
Copy link
Contributor

holanita commented Sep 27, 2022

Why: this ticket is to help us track the progress of the project team (Ismael, Tamara, Zane + Asim, Anita)
What: Anita will be updating this ticket weekly / as needed / before each WG call

@holanita holanita changed the title [PM] Kick-off [PM] Kick-off & Progress Oct 3, 2022
@holanita
Copy link
Contributor Author

holanita commented Oct 3, 2022

(WG call on Oct 3)
As discuss in the WG call today, will catch up with Tamara later this week to see how much progress they were able to make with the draft questions. We will work asynchronously in a google doc and we'll meet once we have something tangible to discuss.

@holanita holanita transferred this issue from Green-Software-Foundation/policy-wg Oct 12, 2022
@holanita holanita added this to the M2 [1-Nov-22] Execution milestone Oct 12, 2022
@holanita holanita added the pm project management label Oct 12, 2022
@holanita
Copy link
Contributor Author

holanita commented Oct 14, 2022

(For the WG call on Oct 17)
Meeting done. Progress looks great. Survey seems doable. Draft survey to be shared with the WG on Monday.

Next steps as per GANTT:

  • on Oct 17: WG call to discuss draft survey and confirm survey tool
  • by Oct 20: work async and adjust draft survey if needed
  • on Oct 20: Team call to discuss updates and next steps if needed
  • by Oct 27: Anita to set up survey tool (Survey Monkey) ?
  • on Oct 28: Team call* to review survey tool
  • by Oct 31: work async and adjust survey tool if needed
  • on Oct 31: WG call to discuss and close open questions
  • by Nov 1: finalize survey

@holanita
Copy link
Contributor Author

holanita commented Oct 31, 2022

(For the WG call on Oct 31)

As discussed in the WG call today:

No feedback received on survey and report outline as of Nov 2. Interviews added to spreadsheet.

@holanita
Copy link
Contributor Author

holanita commented Nov 3, 2022

(For the WG call on Nov 14)

Deadlines mapped out in detail:

Overview on tasks due after Nov 14 (to be mapped out in detail in a new comment):

labels: 🟢 survey 🔴 interviews 🔵 research & report

@holanita holanita changed the title [PM] Kick-off & Progress [PM] SOGS Progress Nov 10, 2022
@holanita
Copy link
Contributor Author

From now on, KPIs will be tracked in this spreadsheet. See also this GH ticket.
Only Asim and Anita attended the last team call and Ismael has been out of reach since last week, so some tasks listed above are pending. Steph has started working on scheduling the interviews and we are monitoring survey results.

@Leamsi9 Leamsi9 mentioned this issue Nov 15, 2022
3 tasks
@holanita
Copy link
Contributor Author

The WG call has been cancelled today. Both the interviews and desk research are behind schedule. We are looking for alternative solutions / help to speed things up. We also need to increase are marketing efforts relating to the survey.

@tamigraph
Copy link
Collaborator

The WG call has been cancelled today. Both the interviews and desk research are behind schedule. We are looking for alternative solutions / help to speed things up. We also need to increase are marketing efforts relating to the survey.

I might be able to help out with the desk research and interviews if it will help us stay relatively on track.

@holanita
Copy link
Contributor Author

Thanks @tamigraph! Asim suggested he would take over the interviews with the SC. You had another idea earlier about some additional interviews that might be worth revisiting – see here. Also, we'll have a chat with Ismael to figure out how we can help with the desk research. I'll let you know as soon as I know more.

@holanita
Copy link
Contributor Author

holanita commented Dec 2, 2022

We'll do weekly sprints from now on

@holanita
Copy link
Contributor Author

Great progress with the survey thanks to Avanade (paid options still TBD). No news from Ismael. 2 interviews booked.

@holanita
Copy link
Contributor Author

holanita commented Jan 4, 2023

I'm closing this. New issues have been created to track progress on marketing / research / interviews.

@holanita holanita closed this as completed Jan 4, 2023