Application/Feature Test Plan

Introducion

The Test Plan has been created to communicate the test approach to team members. It includes the objectives, scope, schedule, risks and approach. This document will clearly identify what the test deliverables will be and what is deemed in and out of scope.

Team Members

Role Name Email
PM Collins Rael projectManager@email.com
QA Lead Kaneki Ken qaLead@email.com
QA Engineer Illia Holub qa@email.com
Dev Lead Chuck Posusta devLead@email.com
Developer Fynn Turko developer@email.com
Design Gibb Parara design@email.com

Feature Description

A brief description here of either the overall application test plan or the test plan for the new feature under development.

Feature Name Jira Ticket Product Spec Design Spec
Feature 1 Name TICKET-1 product_spec_link_1 design_spec_link_1
Feature 2 Name TICKET-2 product_spec_link_2 design_spec_link_2

In Scope

Out of Scope

To pass the system integration test, the following criteria must be met:

  • All business processes are supported.
  • All time functions work correctly.
  • Setitngs functions work correctly.
  • The system is easy to use by the end-users.
  • Security controls are in place to prevent unauthorized system access.
  1. Anything listed in out of scope segment will not be tested

Environment

The proposed test environment

Env Var Value
Line Dev/Staging/Prod
Device Phone/Tablet/Desktop
Target Release Date or release version
Platforms iOs/Android/Web/

Test Phases

Required or optional phases for release

Phase Start End Env Test Content Teams
Prototyping Jan 1. Jan 30. Dev Mocked Data Dev Team 1
Integration Feb 1. Feb. 14 Inegration Test data set 1 Dev Team 1, QA Team 1
E2E Feb 14 Feb 24 Integration Test data set 1, 2, and 3 Dev Team 1 and 2, QA Team 1 and 2
Regression Feb 24 Mar 10 Staging All test data required QA Team 1
Release Mar 11 N/A Prod N/A QA Team 1

Estimated Release Date

Estimated release date: DD/MM/YYYY

Testing Planned

Feature 1: Integration of feature one with existing feature 0

Feature 2: Visual validation of feature 2 elements

Test Data

Feature 1 will require no new test data to be created

Feature 2 will require the following new data:

  • New product type 1
  • New product type 1 variation 1
  • New product type 1 variation 2
  • New User Interaction Option 1

External Dependencies

  • Feature 1 has an external dependency on team A which require delivery of jira_link_to_ticket
  • Feature 2 has no external dependencies

Known Risks

This section describes the system or project risks and the contingency plans that should take effect if the project experiences problems.

  • Authorization - Risk level to critical. Should a problem occur, new users will not able to access to application. Correcting a major defect in production could be very expensive.
  • Timer Settings - Risk level moderate to high. Correcting a major defect in production could be very expensive.