title ms.service api_name ms.assetid ms.date ms.localizationpriority
Task.LevelingCanSplit property (Project)
project-server
Project.Task.LevelingCanSplit
493c8e67-08c1-ccf9-6887-8f7315358f67
06/08/2017
medium

Task.LevelingCanSplit property (Project)

True if leveling can create splits in remaining work. Read/write Boolean.

Syntax

expression. LevelingCanSplit

expression A variable that represents a Task object.

Remarks

You can set the LevelingCanSplit property for all tasks in the Resource Leveling dialog box. To access the setting, click Leveling Options on the Resource tab of the Ribbon, and then click Leveling can create splits in remaining work.

[!includeSupport and feedback]