When reporting out how long any step in the pipeline took or even the entire pipeline execution, I think "seconds" should actually be "minutes". Below is an example from this morning
When reporting out how long any step in the pipeline took or even the entire pipeline execution, I think "seconds" should actually be "minutes". Below is an example from this morning
Example:
Start = [2019-03-06 09:17:37]
End = [2019-03-06 09:34:39]
Timing Taken: 17.0001433332761 seconds
It should be: 17.0001433332761 minutes