Questions

Framework

Let's take a look at activated framework:

.. http:example:: http/questions/get-framework.http
   :code:

Enquiries

The participant has the opportunity to contact the administrator through the electronic procurement system regarding the review of the requirements for the participant, specified in the announcement of qualification for the electronic catalog within ten working days from the day of its publication.

During enquiry period, interested parties can ask questions:

.. http:example:: http/questions/ask-question.http
   :code:

All appeals for clarifications and appeals for the elimination of violations are automatically published in the electronic procurement system without identification of the person who addressed the customer.

Author of question will be hashed with his identifier.id plus access token of the framework. This gives us a possibility to determine that at the framework level a certain number of questions came from the same author.

Let's look at asked question:

.. http:example:: http/questions/get-question.http
   :code:

Procuring entity can answer them:

.. http:example:: http/questions/answer-question.http
   :code:

It is allowed to answer the question during the whole enquiryPeriod and between enquiryPeriod.endDate and enquiryPeriod.clarificationUntil. In case procuring entity is answering question after enquiryPeriod.clarificationUntil, the error will be raised:

.. http:example:: http/questions/answer-question-after-clarifications-until.http
   :code:

Only procuring entity has permission to answer the questions:

.. http:example:: http/questions/answer-question-invalid.http
   :code:

To retrieve the questions list:

.. http:example:: http/questions/list-questions.http
   :code:

To retrieve the individual answer:

.. http:example:: http/questions/get-answer.http
   :code:

The presence of a question does not block the transition of the qualification announcement to the next status.

The presence or absence of an answer to the question does not block the transition of the qualification announcement to the next status.

The period during which the participant can apply to the administrator through the electronic procurement system to review the requirements for the participant: the date of publication of the announcement + 10 working days.

It is forbidden to ask or answer question outside the enquiry period:

.. http:example:: http/questions/ask-question-invalid.http
   :code: