When the task Start/End date is in the past then the dates on Gantt don't align with the Days. A screenshot is attached for more clarification.
Forum Reference: https://forum.bryntum.com/viewtopic.php?t=26113
The text was updated successfully, but these errors were encountered:
I don't see anything incorrect in the provided screenshot. The task lasts 4 weeks and its duration is 20 days (4 weeks * 5 days).
Sorry, something went wrong.
No branches or pull requests
When the task Start/End date is in the past then the dates on Gantt don't align with the Days. A screenshot is attached for more clarification.
Forum Reference: https://forum.bryntum.com/viewtopic.php?t=26113