At the moment baselines implement versioning so setting a task baseline #N does automatically set baselines from #0 till #X-1 if any of them doesn't exist.
This logic does not match what MS Project suggests where a baselines are independent from each other.
Need to add a config to turn baselines behavior to that mode.
At the moment baselines implement versioning so setting a task baseline
#N
does automatically set baselines from#0
till#X-1
if any of them doesn't exist.This logic does not match what MS Project suggests where a baselines are independent from each other.
Need to add a config to turn baselines behavior to that mode.
Requested here: https://www.bryntum.com/forum/viewtopic.php?p=110950#p110950