You signed in with another tab or window. Reload to refresh your session.You signed out in another tab or window. Reload to refresh your session.You switched accounts on another tab or window. Reload to refresh your session.Dismiss alert
I am testing the latest 5.3.0 version before pushing the update to production but I found something broken: the splitter between Gantt and resource utilization or scheduler-pro does not move anymore.
Forum post
Hello!
I am testing the latest 5.3.0 version before pushing the update to production but I found something broken: the splitter between Gantt and resource utilization or scheduler-pro does not move anymore.
Check out the example: https://bryntum.com/products/gantt/examples/frameworks/vue/javascript/gantt-schedulerpro/dist/
Try to move the horizontal bar between the components, it is frozen. This used to work ok in 5.2.10
Do you have this bug already in line for solving? Otherwise, I would have to include settings to hide/show the Gantt if I want to release with 5.3.0.
Thanks