CDT 9.10.0 Endgame #23

Closed
93 of 94 tasks
jonahgraham opened this issue Dec 11, 2019 · 2 comments
Closed
93 of 94 tasks

CDT 9.10.0 Endgame #23

jonahgraham opened this issue Dec 11, 2019 · 2 comments
Assignees
Labels
endgame Checklist of TODO lists to finish a release
Milestone

Comments

@jonahgraham
Copy link
Member

jonahgraham commented Dec 11, 2019

This is the Release plan and TODO list for CDT 9.10.0 release, part of the Eclipse 2019-12 Simrel. CDT makes its simrel contribution on +1 day in the release cycle (normally Monday by 10pm UTC).

Steps for M1

Items before M1 +1 day:

  • Create release on PMI
  • Create New and Noteworthy page for the release
  • Update cdt.target to point to new dependency versions
  • Synchronize CDT.setup to cdt.target
  • Update API baseline to last release and resolve any API errors
  • Remove old API error filters if they are no longer relevant
  • Synchronize CDT.setup for API baseline
  • Update help-docs-eclipserun-repo in root pom.xml and bump versions of all the docs plug-ins
  • Increment version of all feature.xml, pom.xml and any other place full version is used. (Easiest way is global find and replace, e.g. s/9.9.0/9.10.0/g and review changes.)
  • Increment version URL in releng/org.eclipse.cdt-feature/p2.inf
  • Increment version URL in EPP's packages/org.eclipse.epp.package.cpp.feature/p2.inf
  • Update comparator.repo in root pom.xml to last release and if there have been any changes since the branch, bump versions of MANIFEST.MFs
  • Update Maven versions (check CI job)
  • Update simrel-site in root pom.xml
  • Ensure the build is stable - it is always better to release a "Green Dot" build
  • Ensure all previous Endgame issues are done.

Items on M1 +0 day:

  • If tracking most recent platform, look for announcement and update cdt.target to M1 Eclipse Platform

Items on M1 +1 day:

Items on M1 +4 day (or shortly after):

  • The final part of the release is to wait for announcement (normally on +4 day) like this on epp-dev and test the EPP build and confirm operation with a +1 to epp-dev mailing
  • If standalone was not included on +1 day Promote a cdt build from jenkins to add the standalone build (STANDALONE_ONLY = true)
  • Add description to the promote-a-build job and the job it promoted.
  • Mark promoted job as Keep forever
  • Reply to email sent on +1 day with links to EPP and standalone debugger. Example on cdt-dev archives.

Steps for M2

Items on M2 +0 day:

  • If tracking most recent platform, look for announcement and update cdt.target to M2 Eclipse Platform

Items on M2 +1 day:

Items on M2 +4 day (or shortly after):

  • The final part of the release is to wait for announcement (normally on +4 day) like this on epp-dev and test the EPP build and confirm operation with a +1 to epp-dev mailing
  • If standalone was not included on +1 day Promote a cdt build from jenkins to add the standalone build (STANDALONE_ONLY = true)
  • Add description to the promote-a-build job and the job it promoted.
  • Mark promoted job as Keep forever
  • Reply to email sent on +1 day with links to EPP and standalone debugger. Example on cdt-dev archives.

Steps for M3

Items before M3 +1 day:

  • Ensure release entry on PMI "Release Date" section it says the appropriate "This release is part of Eclipse IDE ??????".
  • Schedule a release review if it is needed (generally >= 12 months since the last one). Consult EDP for guidance.

Items on M3 +0 day:

  • If tracking most recent platform, look for announcement and update cdt.target to M3 Eclipse Platform

Items on M3 +1 day:

Items on M3 +4 day (or shortly after):

  • The final part of the release is to wait for announcement (normally on +4 day) like this on epp-dev and test the EPP build and confirm operation with a +1 to epp-dev mailing
  • If standalone was not included on +1 day Promote a cdt build from jenkins to add the standalone build (STANDALONE_ONLY = true)
  • Add description to the promote-a-build job and the job it promoted.
  • Mark promoted job as Keep forever
  • Reply to email sent on +1 day with links to EPP and standalone debugger. Example on cdt-dev archives.

Steps for RC1

Items before RC1 +1 day:

  • Ensure there are no API errors

Items on RC1 +0 day:

  • If tracking most recent platform, look for announcement and update cdt.target to RC1 Eclipse Platform

Items on RC1 +1 day:

Items on RC1 +4 day (or shortly after):

  • The final part of the release is to wait for announcement (normally on +4 day) like this on epp-dev and test the EPP build and confirm operation with a +1 to epp-dev mailing
  • If standalone was not included on +1 day Promote a cdt build from jenkins to add the standalone build (STANDALONE_ONLY = true)
  • Add description to the promote-a-build job and the job it promoted.
  • Mark promoted job as Keep forever
  • Reply to email sent on +1 day with links to EPP and standalone debugger. Example on cdt-dev archives.

Steps for RC2

These steps should be done before RC2 release, they can be completed at anytime between the last branch creation/release and RC2.

Items before RC2 +1 day:

Items on RC2 +0 day:

  • If tracking most recent platform, look for announcement and update cdt.target to RC2 Eclipse Platform

Items on RC2 +1 day:

Items on RC2 +4 day (or shortly after):

  • The final part of the release is to wait for announcement (normally on +4 day) like this on epp-dev and test the EPP build and confirm operation with a +1 to epp-dev mailing
  • If standalone was not included on +1 day Promote a cdt build from jenkins to add the standalone build (STANDALONE_ONLY = true)
  • Add description to the promote-a-build job and the job it promoted.
  • Mark promoted job as Keep forever
  • Reply to email sent on +1 day with links to EPP and standalone debugger. Example on cdt-dev archives.

Steps for Release

Items for quiet week (between RC2 and release):

  • Make sure documentation is part of simrel's help.

Items to be done 2 days before release:

  • Promote a cdt build from jenkins to releases (run twice so standalone is promoted too if needed)
  • Add description to the promote-a-build job and the job it promoted.
  • Unmark as keep all old Milestone and RC jobs
  • Update or create composites in cdt-infra in preparation for going public on release day

Release day:

Items after the release:

  • Delete download.eclipse.org/tools/cdt/builds for this release (e.g:
# Keep a backup on archive temporarily
ssh build.eclipse.org rsync -aAXv /home/data/httpd/download.eclipse.org/tools/cdt/builds /home/data/httpd/archive.eclipse.org/tools/cdt
ssh build.eclipse.org mv -v /home/data/httpd/archive.eclipse.org/tools/cdt/builds/9.10 /home/data/httpd/archive.eclipse.org/tools/cdt/builds/9.10-scheduled-for-deletion
ssh build.eclipse.org rm -rv /home/data/httpd/download.eclipse.org/tools/cdt/builds/9.10 
@jonahgraham jonahgraham added the endgame Checklist of TODO lists to finish a release label Dec 11, 2019
@jonahgraham jonahgraham added this to the CDT 9.10.0 milestone Dec 11, 2019
@jonahgraham jonahgraham self-assigned this Dec 11, 2019
@jonahgraham
Copy link
Member Author

Remove old API error filters if they are no longer relevant

This wasn't done for 9.10, it is done for 9.11 (on master) already.

@jonahgraham
Copy link
Member Author

That's it. CDT 9.10.0 is done.

Sign up for free to subscribe to this conversation on GitHub. Already have an account? Sign in.