5.0.0-M7 Milestone Plan #2935

Closed
66 tasks done
bmicklea opened this issue Oct 28, 2016 · 0 comments
Closed
66 tasks done

5.0.0-M7 Milestone Plan #2935

bmicklea opened this issue Oct 28, 2016 · 0 comments
Labels
kind/planning A checklist of issues for planning a particular sprint.
Milestone

Comments

@bmicklea
Copy link

bmicklea commented Oct 28, 2016

Milestone Overview

  • Visual stack editor
  • SSH improvements
  • Improved Che mount container utility
  • Compose improvements
  • Clarified snapshotting language

Upgrade and Migration

This is a pre-GA milestone in the new Che 5 stream.

Due to a fundamental model change that allows us to deliver multi-machine support, it will only be possible to migrate 4.7.1 workspaces to 5.0.0 at GA (users who wish to try 5.0.0 milestone releases today will have to create new workspaces).

Docker Image Tags
While 5.0 is pre-GA the :latest tags on our Docker images will continue to point to 4.7.1. We will also create a new 5.0.0-latest tag to make it easier to try each 5.0.0 milestone release.

For more information about our development process please see our development process page.

Schedule

This release will be an Eclipse-signed and marketed release.

  • Code complete milestone: Target: November 9, 2016
  • GitHub release complete (QA verified) milestone: Target: November 11, 2016

Schedule Detail

Code complete milestone

  • Milestone issues complete
  • Smoke tests started

Release candidate created milestone

  • Release candidate created
  • Test cycles started
  • Docs complete

GitHub release complete (QA verified) milestone

  • Release completed and QA verified
  • Release notes updated
  • Final release information updated on GitHub
  • Docs reviewed and live

Target Milestone Issues

@bmicklea bmicklea added the kind/planning A checklist of issues for planning a particular sprint. label Oct 28, 2016
@bmicklea bmicklea added this to the 5.0.0-M7 milestone Oct 28, 2016
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
kind/planning A checklist of issues for planning a particular sprint.
Projects
None yet
Development

No branches or pull requests

1 participant