Task 1: Define Data and Information Gathering Plan (5 days)
Task 2: Conduct ICMS Workshops (15 days)
Task 3: Analyze Gathered Data (10 days)
Task 1: Define Portal Requirements (5 days)
Task 2: Develop Community Reporting Portal (20 days)
Task 3: Testing and Debugging (5 days)
Task 1: Code Review and Analysis (10 days)
Task 2: Code Update and Refactoring (25 days)
Task 3: Conduct OSAEC Workshops (5 days)
Task 1: Database Analysis (7 days)
Task 2: Database Restructuring (10 days)
Task 3: Testing Database Relationships (3 days)
Task 1: Develop Test Cases (5 days)
Task 2: Execute Functional Testing (7 days)
Task 3: Bug Fixing (2 days)
Task 1: Deployment Planning (3 days)
Task 2: Deploy System to Live Environment (3 days)
Task 3: Post-Deployment Bug Fixes (1 day)
Task 1: Vulnerability Assessment (4 days)
Task 2: Penetration Testing (2 days)
Task 3: Remediation of Vulnerabilities (1 day)
The text was updated successfully, but these errors were encountered:
lightdcreator
koykoy027
No branches or pull requests
Data and Information Gathering and ICMS Workshops (30 days)
Task 1: Define Data and Information Gathering Plan (5 days)
Task 2: Conduct ICMS Workshops (15 days)
Task 3: Analyze Gathered Data (10 days)
Creation of a Community Reporting Portal with Notifications (30 days)
Task 1: Define Portal Requirements (5 days)
Task 2: Develop Community Reporting Portal (20 days)
Task 3: Testing and Debugging (5 days)
Updating of Deprecated and Old Codes. OSAEC Workshops (40 days)
Task 1: Code Review and Analysis (10 days)
Task 2: Code Update and Refactoring (25 days)
Task 3: Conduct OSAEC Workshops (5 days)
Overall Database Relationship Management for Data Harmonization (20 days)
Task 1: Database Analysis (7 days)
Task 2: Database Restructuring (10 days)
Task 3: Testing Database Relationships (3 days)
Task 3: Testing Database Relationships (3 days)
Test the Functionalities (14 days)
Task 1: Develop Test Cases (5 days)
Task 2: Execute Functional Testing (7 days)
Task 3: Bug Fixing (2 days)
Live Deployment and Fix Any Functionality Issues (7 days)
Task 1: Deployment Planning (3 days)
Task 2: Deploy System to Live Environment (3 days)
Task 3: Post-Deployment Bug Fixes (1 day)
VAPT Testing (7 days)
Task 1: Vulnerability Assessment (4 days)
Task 2: Penetration Testing (2 days)
Task 3: Remediation of Vulnerabilities (1 day)
Documentation Backup and Turnover (1 day)