tocdepth

Provenance

This document was generated based on the contents of the lsst-dm/milestones repository, version 422a78e8, dated 2022-12-11. This corresponds to the status recorded in the project controls system for October 2022.

Top milestones

  • 2023-01-31 : TMA Handoff to Rubin (T&SC-0400-1730)
  • 2023-05-12 : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
  • 2023-09-29 : EPO Construction Finish (EPOC285)
  • 2023-12-05 : Camera Ready for Full System AI&T (COMC-060200-20930)
  • 2023-12-21 : Dome Complete (T&SC-0400-0950)
  • 2024-03-11 : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
  • 2024-07-09 : System First Light (LSST-1520)
  • 2024-11-04 : Test report: Final Pipelines Delivery (LDM-503-17a)
  • 2024-11-04 : COMP: Science Validation 2 Data Release Complete (COMC-0654-0430)
  • 2024-11-11 : Operation Readiness Review Complete (SITCOM-130)

A public HTML version for embedding is here.

Supporting milestones

  • 2020-12-31 : ComCam Ops Readiness (LDM-503-11a) Completed 2020-12-31
  • 2022-09-30 : User Interfaces Complete (EPO-M6) Completed 2022-09-30
  • 2022-09-30 : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304) Completed 2022-09-30
  • 2022-10-03 : Completion of the Scheduler (DM-27734)
  • 2022-10-03 : Start SV Data Collection (COMC-0140)
  • 2022-10-03 : M2 coating decision (SITCOM-127)
  • 2022-10-03 : M2 Glass installed on Cell (SITCOM-104)
  • 2022-10-03 : Optical testing on TMA complete (SITCOM-116)
  • 2022-11-17 : M2 Installed on Telescope (T&SC-1100-0300)
  • 2022-12-20 : COMP: Camera Ready for Verification Testing (ITC00475_COM)
  • 2022-12-28 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92)
  • 2023-02-07 : M2 Software demonstrated (DM-35988)
  • 2023-03-30 : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
  • 2023-05-05 : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
  • 2023-05-31 : OCS Available on Summit (DM-35987)
  • 2023-05-31 : TCS Demonstrated (DM-35989)
  • 2023-06-07 : LSSTCam Received @ Summit (SUMMIT-2976)
  • 2023-07-04 : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
  • 2023-07-17 : ComCam + PF re-Installed on TMA (SITCOM-105)
  • 2023-11-01 : Love Contract Complete (LSST4820)
  • 2023-12-05 : Ops rehearsal for data release processing #1 (LDM-503-13)
  • 2023-12-05 : LSSTCam reverification complete (SITCOM-125)
  • 2024-02-09 : LSSTCam Installed on TMA (SITCOM-123)
  • 2024-03-11 : M1M3 installed on the TMA (SITCOM-110)
  • 2024-03-29 : LSSTCam Cold (New1135)
  • 2024-04-23 : Full focal plane readout complete (New1110)
  • 2024-05-07 : Telescope Aligned (New1165)
  • 2024-07-09 : Ops rehearsal for data release processing #3 (LDM-503-16)
  • 2024-07-09 : Solar System Processing pipeline available. (DM-AP-17)
  • 2024-11-04 : Full integration of the Alert Production system within the operational environment. (DM-AP-16)

Block Schedule

Download the PDF of this Block Schedule here.