You can use the Projects form to attach a Fixed-price or Investment project to a different Estimate project.
-
Click Project management and accounting > Common > Projects > All projects.
-
Select or open the Fixed-price or Investment project to attach to a different Estimate project.
-
On the Action Pane, on the Project tab, in the Maintain group, click Edit.
-
Depending on your version of the program, do one of the following:
-
In Microsoft Dynamics AX 2012 R2: In the Projects form, on the Revenue recognition FastTab, in the Estimate project ID field, select the Estimate project to attach the project to.
-
Otherwise, in the Projects form, on the Setup FastTab, in the Estimate project ID field, select the Estimate project to attach the project to.
-
Note
Only Estimate projects that are in the same project group as the Fixed-price or Investment project are available for selection.