Case Studies

Network schematics

Strategic Permian demo network.

Strategic Permian demo network.

Strategic toy case study network.

Strategic toy case study network.

Strategic small case study network.

Strategic small case study network.

Strategic treatment demo network.

Strategic treatment demo network.

Comparison table

Strategic model Permian demo Strategic model toy case study Strategic model small case study Strategic model treatment demo Operational model case study
Input file strategic_permian_demo.xlsx strategic_toy_case_study.xlsx strategic_small_case_study.xlsx strategic_treatment_demo.xlsx operational_generic_case_study.xlsx
Model type Strategic Strategic Strategic Strategic Operational
Description A representative example of a Permian system. Nearly identical to treatment demo, but with reduced CAPEX options. A very small, toy-sized network. Useful for testing and debugging. Larger network, but "small" in the sense that disposal and pipeline expansion are not allowed, so the model solves quickly. Larger network, and disposal and pipeline expansion are allowed. Takes a bit longer to solve. This can be seen as the "default" case study for the strategic model. Generic case study for the operational model. Note that this case study cannot currently be run in PARETO UI - it can only be run using the Python command line interface.
Decision period Week Week Week Week Day
Decision horizon 52 weeks 52 weeks 52 weeks 52 weeks 5 days
Network nodes 28 9 28 28 0
Production pads 14 4 15 14 5
Production tanks N/A N/A N/A N/A 14
Completions pads 3 1 4 3 1
External completions pads1 1 (CP03) 0 0 1 (CP03) N/A
Disposal sites (SWD) 5 2 3 5 2
Disposal expansion allowed?2 Yes, for K03 and K05 No No Yes, for K03 and K05 No
Storage sites 3 1 2 3 0
Storage expansion allowed? Yes Yes No Yes No
Completions pad No No Yes No Yes
Treatment sites 6 Non-desalination sites: R02, R04, R05 Desalination sites: R01, R03, R06 All sites have zero initial treatment capacity 2 Non-desalination site: R02 Desalination site: R01 Both sites have zero initial treatment capacity 2 Both are non-desalination sites Both sites have nonzero initial treatment capcity 6 Non-desalination sites: R02, R04, R05 Desalination sites: R01, R03, R06 All sites have zero initial treatment capacity 2
Treatment technologies Non-desalination: CB, CB-EV Desalination: FF Non-desalination: CB, CB-EV Desalination: MVC, MD, OARO Non-desalination: CB Non-desalination: CB, CB-EV Desalination: FF, HDH N/A
Treatment expansion allowed? Yes, except for R01 Yes Yes (but only one capacity option) Yes No
Pipeline expansion allowed? Yes Yes No Yes No
Hydraulics settings Roughness factor: 110 Head loss: 0.03 Roughness factor: 110 Head loss: 0.03 Roughness factor: 110 Head loss: 0.03 Roughness factor: 110 Head loss: 0.03 N/A
Economics Discount rate: 8% CAPEX lifetime: 20 years Discount rate: 8% CAPEX lifetime: 20 years Discount rate: 8% CAPEX lifetime: 20 years Discount rate: 8% CAPEX lifetime: 20 years N/A
Notes Recommend solving with Gurobi, or with >15min runtime with CBC. Recommend solving with Gurobi.

Abbreviations

  • CB: Clean brine treatment
  • CB-EV: Clean brine treatment with enhanced evaporation
  • FF: Falling film evaporation
  • HDH: Humidification-dehumidification
  • MD: Membrane distillation
  • MVC: Mechanical vapor compression
  • OARO: Osmotically assisted reverse osmosis
  • SWD: Salt water disposal

  1. In the strategic model, external completions pads can be used to model opportunities for water sharing outside of the main network.

  2. In the strategic model, disposal capacity expansion is only allowed for SWD sites for which the initial disposal capacity is 0.