Incorrect Project Task Start/Finish Dates when created from Project Template #9230
Labels
Area: Module
Issues & PRs related to modules that do not have specific label
Priority:Important
Issues & PRs that are important; broken functions, errors - there are workarounds
Type: Bug
Bugs within the core SuiteCRM codebase
When using the "Create Project" function from the Project - Templates module, the expected Start/Finish dates are not found in the Project Tasks that are created in the new Project.
Steps to Reproduce
Using the Demo CRM
Create a new Project - Template and save
Add first task, with duration 5 days
Add a second Task, with duration 5 days and first task as predecessor
Add a third task, with duration 5 days, with no predecessor
Create a project from this template.
Turn on Consider Working days, and create another project from this template.
Expected Behaviour
1/ The third task should begin on the project start date.
2/ Switching off Consider Working days should change the behaviour of the tasks so they take 5 days instead of 7.
Actual Behaviour
1/ The third task starts on the day after task 2, despite not having any predecessor
2/ Switching on/off Consider Working days has no impact on the Project timing
Context
It makes it impossible to setup a Project Template with parallel workstreams on the Gantt view.
Your Environment
Demo CRM, today
The text was updated successfully, but these errors were encountered: