Project > Milestone > Task Relationships #123

Open
cjsigler opened this issue Jul 24, 2015 · 0 comments
Open

Project > Milestone > Task Relationships #123

cjsigler opened this issue Jul 24, 2015 · 0 comments

Comments

@cjsigler
Copy link

Having a hard time finding much documentation and wanted to make sure the behavior I am experiencing is as designed.

Project: edit project start and end date
No impact to child milestones nor tasks

Milestone: edit end date on milestone
No impact to Project start nor end dates.
No impact to children of this milestone.
All subsequent milestones and their children moved out.

Task: edit end date
No impact to Project start nor end dates.
No impact to parent milestone.
Subsequent sibling tasks moved out.
No impact to subsequent milestones nor their children.

Gant: Click Project Config, enter 25 days excluding weekend work.
Changed Project end date.
No impact to milestones nor their children.