Project Brief, The Collab Lab

Smart Shopping List

Locations for things

Project cadence & duration

The project is expected to take 40 hours per participant, spread over 8 weeks.

Each week, the team of 4 developers will split into 2 pairs of 2 developers each. Each pair will take on a story or task from the issues list to work on together that week.

Pairings will go as follows:

Week 1, January 8 - 14

  1. Jenna & Nina
  2. Jeff & Nesha

Week 2, January 15 - 21

  1. Nina & Jeff
  2. Jenna & Nesha

Week 3, January 22 - 28

  1. Jeff & Jenna
  2. Nesha & Nina

Week 4, January 29 - February 4

  1. Jenna & Nina
  2. Jeff & Nesha

Week 5, February 5 - 11

  1. Nina & Jeff
  2. Jenna & Nesha

Week 6, February 12 - 18

  1. Jeff & Jenna
  2. Nesha & Nina

Week 7, February 19 - 25

  1. Jenna & Nina
  2. Jeff & Nesha

Week 8, February 26 - March 4

  1. Nina & Jeff
  2. Jenna & Nesha