Release schedule

We are currently in a very active development phase and open beta. This means that we push new features to production after only rudimentary testing, and accept that some bugs might be found in production. In a later phase of development we will become more conservative and test our releases more thoroughly before going live. One step towards this, now that we are preparing for a "soft launch", is adopting structured release cycles. These cycles will be short while we are still in open beta.

We should aim to push a new version of Cobudget to production on Thursday afternoon every other week. Every other Monday afternoon, three days before a new version goes live, the 'main' branch is frozen for new updates, except for bug-fixes that are found while testing the release candidate. Sometimes fixing bugs takes longer than three days, and then we postpone pushing the new release candidate live.

We adopt this schedule to fit with that many in our team have a co-working day scheduled on Tuesdays, so that is when testing could be done most efficiently. Pushing to production on Thursday afternoons gives us two days to fix bugs that are found during Tuesday testing, and we have Friday before the weekend to find and fix any bugs that might have been introduced as other bugs were fixed.

Branches

We use three branches for our release cycle.

main is our active development and staging branch. It gets automatically deployed to staging.cobudget.com. Everyone works from the assumption that they should keep their own WIP branches in sync with 'main'.

production is our production branch. It gets automatically deployed to cobudget.com.

Merging

Almost all updates should be made from feature branches to 'main' for testing.

In some cases, if two people are working on large WIP features that touch the same code, they may want to also keep their respective branches in sync with each other.

Small bug fixes and minor fixes can be pushed straight to 'production', but they must then also be immediately merged to 'main'.

In summary, this is the order of merging:

If 'main' is not frozen

feature-branch -> main

If update is a small hotfix

feature-branch -> production -> main

When a new version is released

main -> production

Responsibilities

Product owner (currently @aerugo) is responsible for:

  • Making changes to the protocol
  • Deciding if a release candidate is stable enough to push to production
  • Notifying developers about when the main branch is frozen
  • Deciding if we need longer or shorter release cycles

Developers are responsible for:

  • Keeping their dev branches in sync
  • Merging their updates according to the protocol