Zero Order Costing Package

.. currentmodule:: watertap.costing.zero_order_costing

The zero order costing module contains the costing package typically used for zero order models, though it can also be used for high-fidelity models. Technoeconomic data used for zero order models is contained in the .yaml file for that model located in the data/techno_economic folder.

Usage

The ZeroOrderCosting class contains all the variables and constraints needed to cost a unit model derived from the :ref:`ZeroOrderBaseData`. It also inherits the functionality of the :ref:`WaterTAPCostingBlockData`.

The code below shows an outline of how the ZeroOrderCostingData class is intended to be used to cost zero-order type models.

from pyomo.environ import ConcreteModel

from idaes.core import FlowsheetBlock

from watertap.costing.zero_order_costing import ZeroOrderCosting
from watertap.core.wt_database import Database
from watertap.core.zero_order_properties import WaterParameterBlock
from watertap.unit_models.zero_order import MyZOUnit


m = ConcreteModel()
m.db = Database()
m.fs = FlowsheetBlock(dynamic=False)
m.fs.params = WaterParameterBlock(solute_list=["comp_a", "comp_b", "comp_c"])
m.fs.costing = ZeroOrderCosting()
m.fs.unit = MyZOUnit(property_package=m.fs.params, database=m.db)

# Add necessary statements to fix component flows prior to solve

Costing Zero Order Models

The ZeroOrderCostingData class includes variables and constraints necessary to calculate process-wide costs:

Cost Variable Name Description
Total capital cost C_{ZO,tot} total_capital_cost Total capital cost
Unit capital cost C_{ZO,u} aggregate capital_cost Unit processes capital cost
Total operating cost C_{op,tot} total_operating_cost Total operating cost for unit process
Total fixed operating cost C_{op,fix} total_fixed_operating_cost Total fixed operating cost for unit process
Total variable operating cost C_{op,var} total_variable_operating_cost Total variable operating cost for unit process
Land cost C_{land} land_cost Cost of land for unit process
Working capital cost C_{work} working_capital Working capital for unit process
Salary cost C_{sal} salary_cost Salary cost for unit process
Benefits cost C_{ben} benefits_cost Benefits cost for unit process
Maintenance cost C_{maint} maintenance_cost Maintenance cost for unit process
Laboratory cost C_{lab} laboratory_cost Laboratory cost for unit process
Insurance & taxes cost C_{ins} insurance_and_taxes_cost Insurance & taxes for unit process
Total annualized cost C_{annual} total_annualized_costs Total cost on a annualized basis

Calculations for each of these costs are presented below.

Costing Index and Technoeconomic Factors

Costing indices are available in default_case_study.yaml located in the data/techno_economic folder.

WaterTAP uses the CE (Chemical Engineering) Cost Index to help account for the time-value of investments and are used in the capital and operating cost calculations. Unit process capital costs are adjusted to the year of the case study. The default year is 2018.

Other technoeconomic factors used to calculate various system metrics, capital, and operating costs are presented in the table below:

Cost factor Variable Name Default Value Description
Plant capacity utilization factor f_{util} utilization_factor 100% Percentage of year plant is operating
Plant lifetime L plant_lifetime 30 yr Expected lifetime of unit process
Electricity price P electricity_cost $0.0595/kWh Electricity price in 2019 USD.
Land cost factor f_{land} land_cost_percent_FCI 0.15% Unit process land cost as percentage of capital cost
Working capital cost factor f_{work} working_capital_percent_FCI 5% Unit process working capital cost as percentage of capital cost
Salaries cost factor f_{sal} salaries_percent_FCI 0.1% Unit process salaries cost as percentage of capital cost
Maintenance cost factor f_{maint} maintenance_costs_percent_FCI 0.8% Unit process maintenance costs as percentage of capital cost
Lab cost factor f_{lab} laboratory_fees_percent_FCI 0.3% Unit process laboratory costs as percentage of capital cost
Insurance/taxes cost factor f_{ins} insurance_and_taxes_percent_FCI 0.2% Unit process insurance & taxes cost as percentage of capital cost
Benefits cost factor f_{ben} benefit_percent_of_salary 90% Unit process benefits cost as percentage of salary costs
Weighted average cost of capital factor f_{wacc} wacc 5% Weighted average cost of capital over plant lifetime
Capital recovery factor f_{crf} capital_recovery_factor 6.51% Calculated from default f_{WACC} and L values

The capital recovery factor is calculated with:

f_{crf} = \frac{ f_{wacc} (1 + f_{wacc}) ^ L}{ (1 + f_{wacc}) ^ L - 1}

Capital Cost Calculations

In general, unit process capital costs C_{ZO,u} for zero order unit models are a function of flow:

C_{ZO,u} = A \bigg( \frac{Q_{in}}{Q_{basis}} \bigg) ^ {B}

Q_{basis}, A, and B are specific to the unit model and can be found in the unit model .yaml file. The A value has units of USD for the costing reference year of the unit. For example, if the unit costing model is from a reference that used 2015 USD, the units for A are USD_2015. After calculating the costs in 2015 USD, WaterTAP adjusts the cost to the user-specified year via the Consumer Price Index.

The total capital cost of a zero order model C_{ZO,tot} includes the land cost C_{land} and working capital costs C_{work}:

C_{ZO,tot} = C_{ZO,u} + C_{land} + C_{work}

Where:

& C_{land} = f_{land} C_{ZO,u} \\\\
& C_{work} = f_{work} C_{ZO,u}

Custom Capital Cost Methods

There are several zero order models that have costing relationships that do not follow this general form. If that is the case, a custom costing method can be added to the unit model class to perform that calculation.

Zero order models that have custom capital costing methods include:

  • Brine concentrator - cost_brine_concentrator()
  • CANDOP - cost_CANDOP()
  • Chemical addition - cost_chemical_addition()
  • Chlorination - cost_chlorination()
  • Coagulation/Flocculation - cost_coag_and_floc()
  • Deep well injection - cost_deep_well_injection()
  • DMBR - cost_dmbr()
  • Electrochemical nutrient removal - cost_electrochemical_nutrient_removal()
  • Evaporation pond - cost_evaporation_pond()
  • Filter press - cost_filter_press()
  • Fixed bed - cost_fixed_bed()
  • GAC - cost_gac()
  • Landfill - cost_landfill()
  • MABR - cost_mabr()
  • Ion exchange - cost_ion_exchange()
  • Iron/Manganese removal - cost_iron_and_manganese_removal()
  • Metab - cost_metab()
  • Nanofiltration - cost_nanofiltration()
  • Ozone - cost_ozonation()
  • Ozone + AOP - cost_ozonation_aop()
  • Photothermal membrane - cost_photothermal_membrane()
  • Sedimentation - cost_sedimentation()
  • Storage tank - cost_storage_tank()
  • Surface discharge - cost_surface_discharge()
  • UV irradiation - cost_uv()
  • UV + AOP - cost_uv_aop()
  • Well field - cost_well_field()

To add a custom capital calculation method, the unit model class must register its custom costing method by setting its default_costing_method attribute.

Operating Cost Calculations

Total operating costs for zero order models C_{op,tot} include fixed C_{op,fix} and variable operating costs C_{op,var}:

C_{op,tot} = C_{op,fix} + C_{op,var}

The total fixed operating costs are calculated as:

C_{op,fix} = C_{sal} + C_{ben} + C_{maint} + C_{lab} + C_{ins}

Where:

& C_{sal} = f_{sal} C_{ZO,u} \\\\
& C_{ben} = f_{ben} C_{sal} \\\\
& C_{maint} = f_{maint} C_{ZO,u} \\\\
& C_{lab} = f_{lab} C_{ZO,u} \\\\
& C_{ins} = f_{ins} C_{ZO,u}

Variable operating costs include any chemical additions, electricity costs, and other variable costs such as equipment replacements.

C_{op,var} = C_{chem} + C_{elec} + C_{other} + C_{op,tot}

Chemical costs are based on the chemical dosage for a given chemical addition. Default chemical costs are found in default_case_study.yaml. The annual chemical costs are calculated as:

C_{chem} = \sum_{k}^{n} D_k C_k Q_{in} f_{util}`

Where D is the dose of chemical k and C is the unit cost of chemical k.

Electricity costs C_{elec} are based on the energy intensity E of the unit process (see individual unit model documentation for details). The annual electricity costs are calculated as:

C_{elec} = E Q_{in} f_{util} P

LCOW Calculation

The Levelized Cost Of Water (LCOW) [$/m3] is a metric used to assess the technoeconomics of a unit process:

LCOW = \frac{ f_{crf} C_{ZO,tot} + C_{op,tot} }{Q f_{util} }

Other aggregates, like specific energy consumption, are provided through the :ref:`WaterTAPCostingBlockData`: :ref:`technical_reference/costing/costing_base:Aggregates Metrics`.

Class Documentation