TC ID | Date Run | Priority | Run By | Results | Explanation |
---|---|---|---|---|---|
GPM.NG_BTN | 23.05.2024 | H | Doğa Melis ERKE | Pass | New game has been loaded. |
GPM.LG_BTN | 23.05.2024 | H | Doğa Melis ERKE | Pass | The saved game has been loaded. |
GPM.EG_BTN | 23.05.2024 | M | Doğa Melis ERKE | Pass | The game has been closed and returned to the desktop. |
GPM.STNGS_BTN | 23.05.2024 | M | Doğa Melis ERKE | Pass | The settings window has been opened. |
GPM.MV_SLDR | 23.05.2024 | L | Doğa Melis ERKE | Fail | Could not adjust the music volume via the slider. |
GPM.Windowed_CB | 23.05.2024 | L | Ege ÖZÇELİK | Pass | The “Window” button was selected by checking the windowed checkbox. |
GPM.CT_BTN | 23.05.2024 | L | Ege ÖZÇELİK | Pass | Provides tile catalog on click. |
GPM.A_SPW | 23.05.2024 | L | Ege ÖZÇELİK | Pass | Animals spawn when specific conditions are met. |
GPM.Save_BTN | 23.05.2024 | L | Ege ÖZÇELİK | Pass | Pressing the save button saves the current game to be loaded later. |
GPM.Cancel_BTN | 23.05.2024 | L | Özgün DOĞAN | Pass | Pressing the cancel button closes settings |
GPM.QG_BTN | 23.05.2024 | M | Özgün DOĞAN | Pass | When pressing quit game button the player is directed to main menu |
GPM.PAB_BTN | 23.05.2024 | H | Özgün DOĞAN | Fail | This button will not be present in the last release |
GPM.Pause_BTN | 23.05.2024 | L | Özgün DOĞAN | Pass | When pressing the pause button The simulation will be stopped. |
GPM.Cont_BTN | 23.05.2024 | L | Emre ERİŞEN | Pass | When pressing the continue button the simulation will continue. |
GPM.R_P | 23.05.2024 | H | Emre ERİŞEN | Pass | Resource panel shows present resources to use |
GPM.AP_P | 23.05.2024 | H | Emre ERİŞEN | Pass | Animal population panel shows animal counts |
TC ID | Date Run | Priority | Run By | Results | Explanation |
---|---|---|---|---|---|
GPM.CM.01 | 23.05.2024 | H | Emre ERİŞEN | Pass | Successfully moved forward by pressing the 'w' button. |
GPM.CM.02 | 23.05.2024 | H | Emre ERİŞEN | Pass | Efficiently moved backward using the 's' button. |
GPM.CM.03 | 23.05.2024 | H | Emre ERİŞEN | Pass | Navigated to the right smoothly with the 'd' button. |
GPM.CM.04 | 23.05.2024 | H | Emre ERİŞEN | Pass | Navigated to the left smoothly with the 'a' button. |
GPM.CM.05 | 23.05.2024 | H | Emre ERİŞEN | Pass | Rotated to the left seamlessly by pressing the 'q' button. |
GPM.CM.06 | 23.05.2024 | H | Emre ERİŞEN | Pass | Rotated to the right seamlessly by pressing the 'e' button. |
GPM.CM.07 | 23.05.2024 | H | Özgün DOĞAN | Pass | The map zoomed in when the mouse wheel was scrolled up. |
GPM.CM.08 | 23.05.2024 | H | Özgün DOĞAN | Pass | The map zoomed out when the mouse wheel was scrolled down. |
Priority | Number of TCs | Executed | Passed |
---|---|---|---|
H | 13 | 13 | 12 |
M | 3 | 3 | 3 |
L | 8 | 8 | 7 |
Total | 24 | 24 | 22 |
We have successfully executed a total of 24 test cases out of which 22 have passed. Notably, 12 high-priority test cases have also been successfully passed along with all medium-priority test cases. Given these results, we are pleased to confirm that the exit criteria have been fully met.
Exit Criteria | Status |
---|---|
Test Coverage: | |
- All test cases executed | Met |
- 95% or more test cases passed | Met |
- 95% or more high and medium priority test cases passed | Met |
Critical Functionality: | |
- No outstanding high priority or severe bugs | Met |
- Essential functionalities pass without critical issues | Met |
Stability and Performance: | |
- Essential functionalities perform within acceptable parameters | Met |
Specific Functionality: | |
- All essential functionalities pass testing. | Met |
- The music volume adjustment via the slider failed in the current version but will be addressed in the next release.
- The presence of the "PAB" button which was marked for removal still exists in the current version.
The software meets the defined exit criteria with a high percentage of test cases passing and critical functionalities operating without major issues. However, two known problems exist which require attention in future releases. Overall, the software is ready for deployment or delivery, meeting quality, budget, and timeline expectations.