pv system sizing issue #54

Closed Answered by t-gross
aziz333999 asked this question in Q&A
Apr 29, 2024 · 1 comments · 1 reply
Discussion options

You must be logged in to vote

Thanks for your question.
I think the problem is how you specified the maximum operation rate values for the PV component.
In the documentation, you can find the following hint:

        :param operationRateMax: if specified, indicates a maximum operation rate for each location and each time
            step by a positive float. If hasCapacityVariable is set to True, the values are given relative
            to the installed capacities (i.e. a value of 1 indicates a utilization of 100% of the
            capacity). If hasCapacityVariable is set to False, the values are given as absolute values in form
            of the commodityUnit for each time step.

You would need to convert your oper…

Replies: 1 comment 1 reply

Comment options

You must be logged in to vote
1 reply
@aziz333999
Comment options

Answer selected by t-gross