Move to AWS: Plan and test migration and cutover to AWS #4322

Closed
kcondon opened this issue Nov 29, 2017 · 2 comments
Closed

Move to AWS: Plan and test migration and cutover to AWS #4322

kcondon opened this issue Nov 29, 2017 · 2 comments
Assignees

Comments

@kcondon
Copy link
Contributor

kcondon commented Nov 29, 2017

Migration as used here refers to moving production data, config, and files to the AWS environment in such a way to minimize downtime and not lose any changes/ keep it in sync.
Cutover refers to the actual steps and timeline to switch between old production to being hosted on AWS. We need to minimize downtime where possible and understand how long task take and who does them. Also plan for problems -contact lists, rollback.

@landreev
Copy link
Contributor

Finalizing the "Day X" (cutover date) task list.
Will link the document here shortly.

@landreev
Copy link
Contributor