Application.InsertMilestoneTask method (Project)

Inserts a new milestone task above the selected task row or cell in a Gantt chart.

Syntax

expression. InsertMilestoneTask

expression An expression that returns an Application object.

Return value

Boolean

Remarks

The milestone task has a duration of 0 days and is of the default mode (automatically or manually scheduled). The InsertMilestoneTask method corresponds to the Milestone command in the Insert group of the Task tab on the Ribbon.