Skip to content

Status Update ‐ Mid Sprint 4

Raj Palival edited this page Apr 15, 2024 · 2 revisions

Project Jobber Status Update

MID of Sprint 4

Date: 2024-04-08 - 2024-04-15

Major Project Feature Summary:

Status Symbol
Completed
In Progress 🔶
Pending ⛔️

Major Project Feature % completed to date

Feature Status Completion Percentage
Account creation and login page 🔶 75%
User Authentication 🔶 40%
Status Dashboard Homepage 🔶 30%
Resume Parsing 🔶 10%
Company Management System ⛔️ 0%
Contact Management System ⛔️ 0%
Reminder System ⛔️ 0%
Filtering Options 100%
Website Navigation 100%
Analytics Dashboard ⛔️ 0%
Job Tracking Page (Main app) 🔶 70%

Current Project Status Summary: ✅

With the mid of Sprint 4, the project has shifted focus to complete any and all remaining features. We recognize the timetable we have left to complete such features, however the challenges we encountered in the prior sprint have been generally resolved allowing us to push the necessary code.

Team Status Summary:

The team is currently focused to complete the remaining features for the application.

Team Goals for the upcoming week:

  • Homepage Dashboard
  • Complete Authentication and Authorization.
  • Resume Parser.
  • Completed contact and company management systems.
  • Add a reminder system.

Individual Team Member Status:

  • Raj: working on dashboard components and ag-grid update logic

    Next week: continue with dashboard, finish up final login setup, resume upload and create companies and contacts page.

  • Omar: Worked on the remaining functionality for job application page on and refactored the repository code.

  • Next week: Work on remaining feature development.

  • Dev: working on resume upload api

    Next week: job description and resume keywords compiler

  • Arjun: Worked on hosting the front end and updating the backend elastic beanstalk version

    Next week: Working on setting up CI/CD pipeline

  • Amith: Working on google authentication and http pay load api - yet to complete it

    Next week: continue working on google auth and cover up the pending stuffs and work on company and job database.

Past week team activities:

  • Status meeting (ALL) 04/09/2024
  • Development meeting (ALL) 04/14/2024
  • Backend and Frontend Collaboration (Omar and Raj) 04/14/2024

Team Project Decisions:

  • No major decisions of last week.

Other Comments:

  • Expectations for the baseline product remains the same.