The issue is that completion percentage algorithm in GP 2.8.X takes into account task lengths for all tasks, including summary tasks. That's why the completion of a summary task will be different when e.g. two child tasks are chained with a dependency and when they are not (and go in parallel)
This is fixed in the master branch by #1455 but remains in GP 2.8.X.
We'll probably need project open diagnostic code which reports if completion changes with the new algorithm or not.
The text was updated successfully, but these errors were encountered:
Topic on the support portal:
https://help.ganttproject.biz/t/task-completion-calculation/1461
The issue is that completion percentage algorithm in GP 2.8.X takes into account task lengths for all tasks, including summary tasks. That's why the completion of a summary task will be different when e.g. two child tasks are chained with a dependency and when they are not (and go in parallel)
This is fixed in the
master
branch by #1455 but remains in GP 2.8.X.We'll probably need project open diagnostic code which reports if completion changes with the new algorithm or not.