- DATE:01/02/2022
- ASSISTANTS: Mika Oja
We mainly talked about the tasks that were related to deadline 01. Some of the tasks were not done according to the way the instructor expected. The action points section in the following lists the things that needed to be modified.
- Defining a concrete client application.
- Defining a machine-to-machine client.
- Concepts explained need to be changed in a noun-oriented way.
- Diagrams need to be changed so they reflect noun relationships.
ONLY USED BY COURSE STAFF: Additional comments from the course staff
- DATE:15/02/2022
- ASSISTANTS: Mika Oja
Everything was checked by the instructor and we received the full mark for every evaluation regarding DL2.
Since everything was implemented fully, no further actions was required.
ONLY USED BY COURSE STAFF: Additional comments from the course staff
- DATE:15/03/2022
- ASSISTANTS: Mika Oja
Summary of what was discussed during the meeting
List here the actions points discussed with assistants
- Uniform Interface was missing
- Project structure should be changed
- Code quality had some issues
- Some of the documentations were missing
- Decorator converters were required to be changed to utility functions
- PUT methods were missing
ONLY USED BY COURSE STAFF: Additional comments from the course staff
- DATE:
- ASSISTANTS:
Summary of what was discussed during the meeting
List here the actions points discussed with assistants
ONLY USED BY COURSE STAFF: Additional comments from the course staff
- DATE:
- ASSISTANTS:
Summary of what was discussed during the meeting
List here the actions points discussed with assistants
ONLY USED BY COURSE STAFF: Additional comments from the course staff
- DATE:
- ASSISTANTS:
Summary of what was discussed during the meeting
List here the actions points discussed with assistants
ONLY USED BY COURSE STAFF: Additional comments from the course staff