Gate 2 Release Checklist

\

@Sl NoChecklistYes/No/PartiallyReference linkOwnerReviewerRemarks
1Development is completed for all the features that are part of the release.Yes Kaviyarasan PSathish PCode was frozen on 10-Feb-2023
2Test cases are documented by the QA team, reviewed by the product owners and test results are updated in the test cases sheet.YesTest Cases for Digit 2.8 Release

Navyashree G

Keerthi Bhaskara

P. SankarTest cases documents are reviewed and updated
3The incremental demo of the features showcased during the sprint showcase and feedback incorporated. If possible list out the JIRA tickets for feedback.Yes Demos

Kaviyarasan P

P. Sankar

Nirbhay Singh

Yes, incremental demos are shown during the development sprints.
4UI/UX Audit review by UX Architect is completed along with feedback incorporation for any changes in UI/UX.Yes UI/UX Audit Review & Feedback

JaganKumar

Antriksh Kumar

Vamshikrishna Kole

P. SankarUI/UX audit is done and review comments are incorporated.
5Incremental demos to the product owners are completed as part of the sprint and feedbacks are incorporated.YesDemosKaviyarasan PP. SankarIncremental demos are done as per sprint
6QA signoff is completed by the QA team and communicated to the product owners. All the tickets QA signoff status is updated in the JIRA.Yes

Navyashree G

Keerthi Bhaskara

P. Sankar

QA signoff was completed.
Incremental sign-off dates

3rd Nov 2022

  • Water & Sewerage
  • Bill Amendment
  • Bill Genie

13th Dec 2022

  • Property Tax
  • Trade Licence
  • Public Grievance Redressal
  • Online Building Plan Approval System
  • Birth & DeathTabular Reports - in old UI/UX
  • Mis Collection
  • National Dashboard FAQ & About screen
  • Product specific pages
  • Navigation redirection from New UI to old UI

2nd Feb 2023

  • Surveys
7UI, API Technical documents are updated for the release along with the configuration documents. YesRelease Notes, Document Resources & Links

Kaviyarasan P

Vamshikrishna Kole

Featured in the release page and master migration document
8UAT promotion and regression testing from the QA team is completed. QA team has shared the UAT regression test cases with the product owners.Yes Test Cases for Digit 2.8 Release

Navyashree

KeerthiBhaskara-eGov

P. Sankar

9API Automation scripts are updated for new APIs or changes to any existing APIs for the release. API automation regression is completed on UAT, the automation test results are analyzed and necessary actions are taken to fix the failure cases. Publish the list of failure use cases with a reason for failure and the resolution taken to fix these failures for the release.No

Navyashree G

KeerthiBhaskara-eGov

Not picked up in this release due to lack of resources
10The API backward compatibility testing is completed.Yes2.8 ReportsNavyashree GKaviyarasan PUse cases ran with the existing scripts, no new API structure changes in the new release. new scripts for 2.8 will taken up in upcoming sprints
11The communication is shared with the product owners for the completion of UAT promotion and regression by the QA team. The product owners have to give a Product signoff within one week of this communication.Yes

Navyashree G

Keerthi Bhaskara

P. Sankar

UAT sign-off was completed.
Incremental sign-off dates


13th Dec 2022

  • Water & Sewerage
  • Bill Amendment
  • Bill Genie
  • Property Tax
  • Trade License
  • Public Grievance Redressal
  • Online Building Plan Approval System
  • Birth & Death Tabular Reports - in old UI/UX
  • Mis Collection
  • National Dashboard FAQ & About screen
  • Product specific pages
  • Navigation redirection from New UI to old UI
  • National Dashboard Adaptor Integration Testing

6th Feb 2023

  • Surveys

6th Jan 2023

  • Trade L license Reports
  • Online Building Plan Approval System Reports

12th Jan 2023

  • National Dash Board 3 New KPI
  • Finance DSS

9th Feb 2023

  • Fire NOC
12UAT Product Signoff communication is received from the Product owners along with the release notes and User guides (if applicable).YesProduct Release Notes

Kaviyarasan P

Product Owners

P. Sankar

All prods are signed off , release notes and user guides are updates

  • Water & Sewerage
  • Bill Amendment
  • Bill Genie
  • Property Tax
  • Trade Licence
  • Public Grievance Redressal
  • Online Building Permission System
  • Birth& Death Tabular Reports - in old UI/UX
  • Mis Collection
  • National Dashboard FAQ & About screen
  • Product specific pages
  • Navigation redirection from New UI to old UI
  • Surveys
  • Fire NOC
13The GIT tags and releases are created for the code changes for the release.YesService Build Updates 2.8Kaviyarasan P Sathish P
14Verify whether the Release notes are updatedYes Kaviyarasan P Sathish P
15Verify whether all UAT Builds are updated along with the GIT tag details.YesService Build Updates 2.8Kaviyarasan P Sathish P
16Verify whether all MDMS, Configs, InfraOps configs updated.Yes MDMS ConfigKaviyarasan P Sathish P
17Verify whether all docs will be Published to http://urban.digit.org by the Technical Writer as part of the release.Yes

Kaviyarasan P

Anjoo Narayan

Sankar Sathish P
18Verify whether all test cases are up to date and updated along with necessary permissions to view the test cases sheet. The test cases sheet is verified by the Test Lead.Yes Test Cases

Navyashree G

Keerthi Bhaskara

Sankar
19Verify whether the UAT credentials sheet is updated with the details of new Users and Roles if anyYes

Navyashree G

Keerthi Bhaskara

Sankar UAT creds shared internally to product & impel team
20Verify whether all the localisation data was added in UAT including Hindi and updated in Release Kits.YesLocalization

Navyashree G

Keerthi Bhaskara

Kavi
21Verify whether the product release notes and user guides are updated and publishedYesProduct Release NotesNirbhay Singh Satish N Chandra Kiran Sankar Abhishek P. SankarRelease notes and user guides are published in gitbooks.
22The Demo of released features is done by the product team as part of the Sprint/Release showcase.YesDIGIT 2.8 Release ShowcaseNirbhay Singh Satish N Chandra Kiran Sankar Abhishek P. SankarYes - all features of 2.8 are demoed to the eGov team on 15th Feb 2023
23Technical and Product workshops/demos are conducted by the Engineering and Product team to the implementation team (Implementation handover)Yes Kaviyarasan PPradeep KumarMigration process has been explained, all docs are added to the master migration doc based on feedback from impel team
24Architect SignOff and Technical Quality ReportYes Kaviyarasan P Kaviyarasan PSign off is given with privacy disabled and encryption process disabled for W&S, PT modules. Redesign of privacy will be taken up by DPG based on the shortcomings shared in Tech council.
25Success Metrics and Product Roadmap YesSuccess MetricsNirbhay Singh P. Sankar SankarProduct road map post digit 2.8 is not clear yet as we have less visibility and trimming down the operations/resources in urban team.
26Adoption Metrics YesAdoption MetricsAjay Rawat
P. Sankar
Sankar
27Program Roll-out Plan YesProgram Roll Out PlanAjay Rawat Chandar
28Implementation checklist YesImplementation ChecklistPradeep Kumar Elzan
29Implementation Roll-out plan YesUpyog 2.8: Upgrade EstimationPradeep Kumar Elzan
30Gate 2 In-progress Meeting scheduled on 20th Feb 2023Kaviyarasan P, Sathish P, Pradeep Kumar, Ajay Rawat, Sankar, Satish N, Nirbhay Singh, Anjoo Narayan Approver will be added post meeting
31The Internal release communication along with all the release artefacts are shared by the Engineering/Product team. In-progress Kaviyarasan P, Sankar P, Sathish P Sankar Communication will be shared once Gate 2 is passed
32Plan for upgrading the staging/demo instance with the release product - within 2-4 weeks based on the period where no demos are planned from staging for the previous version of the released product. Pradeep Kumar ElzanStaging will be upgraded after the release
33The Release communication to partners is shared by the GTM team and the Webinar is arranged by the GTM team after the release communication - within 2-4 weeks of the release. Vibhor Bansal

\