december and compare to novemver
Browse files Browse the repository at this point in the history
  • Loading branch information
womullan committed Jan 23, 2024
1 parent bcc1ec0 commit 206e428
Show file tree
Hide file tree
Showing 3 changed files with 41 additions and 39 deletions.
2 changes: 1 addition & 1 deletion Makefile
Original file line number Diff line number Diff line change
Expand Up @@ -34,7 +34,7 @@ clean:
# celeb uses fdue forecast dates
.PHONY:
index.rst: milestones blockschedule.pdf
python milestones/milestones.py celeb --inc=Y ;
python milestones/milestones.py celeb --inc=Y --months=1 ;
mv index.rst temp.rst;
@echo "======================" > index.rst;
@echo "Celebratory Milestones" >> index.rst;
Expand Down
76 changes: 39 additions & 37 deletions index.rst
Original file line number Diff line number Diff line change
@@ -1,15 +1,13 @@
======================
Celebratory Milestones
======================
.. Auto-generated by milestones/milestones.py on Mon Jan 22 15:53:54 2024 - DO NOT EDIT
:tocdepth:
.. Auto-generated by milestones/milestones.py on Mon Jan 22 16:13:30 2024 - DO NOT EDIT
Provenance
==========

This document was generated based on the contents of the `lsst-dm/milestones <https://github.com/lsst-dm/milestones>`_ repository, version `88ac8705 <https://github.com/lsst-dm/milestones/commit/88ac870528ca1004023d8bb9a8fbb5afc971fcce>`_, dated 2023-10-17.
This corresponds to the status recorded in the project controls system for September 2023.
This document was generated based on the contents of the `lsst-dm/milestones <https://github.com/lsst-dm/milestones>`_ repository, version `bd418e5e <https://github.com/lsst-dm/milestones/commit/bd418e5e76a2866e4fc4084082309ccd0cf4bb84>`_, dated 2024-01-22.
This corresponds to the status recorded in the project controls system for December 2023.

Top milestones
==============
Expand All @@ -18,25 +16,25 @@ Top milestones

- **2023-03-31** : TMA Handoff to Rubin (T&SC-0400-1730) **Completed 2023-03-31**

- **2024-02-21** : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
- **2024-03-26** : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)

- **2024-05-29** : ComCam Reinstalled on TMA (SUMMIT-Oct24-160)
- **2024-06-17** : ComCam Reinstalled on TMA (SUMMIT-Oct24-160)

- **2024-07-01** : Dome Complete (T&SC-0400-0950)

- **2024-07-03** : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
- **2024-07-22** : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)

- **2024-08-28** : Camera Ready for Full System AI&T (COMC-060200-20930)
- **2024-09-27** : Camera Ready for Full System AI&T (COMC-060200-20930)

- **2024-12-11** : LSSTCam Ready for On Sky (First Photon) (SITCOM-122)
- **2025-01-03** : LSSTCam Ready for On Sky (First Photon) (SITCOM-122)

- **2025-01-24** : System First Light with LSSTCam (LSST-1520)
- **2025-02-18** : System First Light with LSSTCam (LSST-1520)

- **2025-05-22** : Test report: Final Pipelines Delivery (LDM-503-17a)
- **2025-06-16** : Test report: Final Pipelines Delivery (LDM-503-17a)

- **2025-05-22** : COMP: Science Validation Surveys Complete (COMC-0654-0430)
- **2025-06-16** : COMP: Science Validation Surveys Complete (COMC-0654-0430)

- **2025-05-29** : Operation Readiness Review Complete (SITCOM-130)
- **2025-06-23** : Operation Readiness Review Complete (SITCOM-130)

A public HTML version for embedding is `here <./top_milestones.html>`_.

Expand All @@ -55,51 +53,55 @@ Supporting milestones

- **2023-06-30** : Completion of the Scheduler (DM-27734) **Completed 2023-06-30**

- **2023-10-02** : OCS Available on Summit (DM-35987)
- **2023-10-01** : M2 coating decision (SITCOM-127) **Completed 2023-10-01**

- **2023-11-01** : Love Contract Complete (LSST4820) **Completed 2023-11-01**

- **2024-01-02** : OCS Available on Summit (DM-35987)

- **2023-10-02** : TCS Demonstrated (DM-35989)
- **2024-01-02** : TCS Demonstrated (DM-35989)

- **2023-10-02** : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
- **2024-01-03** : ComCam + PF re-Installed on TMA (SITCOM-105)

- **2023-11-08** : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
- **2024-01-08** : TMA safe for transition to M1M3 glass mirror (SITCOM-102)

- **2023-11-09** : ComCam + PF re-Installed on TMA (SITCOM-105)
- **2024-02-05** : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)

- **2023-12-01** : Love Contract Complete (LSST4820)
- **2024-04-23** : LSSTCam Received @ Summit (SUMMIT-2976)

- **2024-01-17** : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
- **2024-05-02** : M2 Software demonstrated (DM-35988)

- **2024-03-29** : M2 Software demonstrated (DM-35988)
- **2024-05-08** : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)

- **2024-04-04** : LSSTCam Received @ Summit (SUMMIT-2976)
- **2024-05-23** : M2 Glass installed on Cell (SITCOM-104)

- **2024-05-06** : M2 coating decision (SITCOM-127)
- **2024-06-11** : M2 Installed on Telescope (T&SC-1100-0300)

- **2024-05-06** : M2 Glass installed on Cell (SITCOM-104)
- **2024-06-24** : M1M3 Mirror Coating completed (SITCOM-109)

- **2024-05-23** : M2 Installed on Telescope (T&SC-1100-0300)
- **2024-07-22** : M1M3 installed on the TMA (SITCOM-110)

- **2024-07-03** : M1M3 installed on the TMA (SITCOM-110)
- **2024-09-27** : LSSTCam reverification complete (SITCOM-125)

- **2024-08-28** : LSSTCam reverification complete (SITCOM-125)
- **2024-11-11** : LSSTCam Installed on TMA (SITCOM-123)

- **2024-10-17** : LSSTCam Installed on TMA (SITCOM-123)
- **2024-12-27** : LSSTCam Cold (New1135)

- **2024-12-04** : LSSTCam Cold (New1135)
- **2025-01-21** : Full focal plane readout complete (New1110)

- **2024-12-27** : Full focal plane readout complete (New1110)
- **2025-01-22** : Telescope Aligned (New1165)

- **2024-12-30** : Telescope Aligned (New1165)
- **2025-02-18** : Solar System Processing pipeline (SSP) available. (DM-AP-17)

- **2025-01-24** : Solar System Processing pipeline (SSP) available. (DM-AP-17)
- **2025-02-18** : Initial Optical testing on TMA complete (SITCOM-116)

- **2025-01-24** : Initial Optical testing on TMA complete (SITCOM-116)
- **2025-02-18** : System First Light with LSSTCam (SITCOM-121)

- **2025-03-03** : Start SV Data Collection (COMC-0140)
- **2025-03-26** : Start SV Data Collection (COMC-0140)

- **2025-05-22** : Full integration of the Alert Production system within the operational environment. (DM-AP-16)
- **2025-06-16** : Full integration of the Alert Production system within the operational environment. (DM-AP-16)

- **2025-05-29** : Ops rehearsal for data release processing #3 (LDM-503-16)
- **2025-06-23** : Ops rehearsal for data processing #3 (LDM-503-16)

.. image:: blockschedule.png
:alt: Block Schedule
Expand Down