.. Auto-generated by milestones/milestones.py on Tue Mar 26 13:07:58 2024 - DO NOT EDIT
.. Auto-generated by milestones/milestones.py on Wed May 1 17:51:17 2024 - DO NOT EDIT
######################
Celebratory Milestones
Expand All @@ -7,10 +7,10 @@ Celebratory Milestones
Provenance
==========

This document was generated based on the contents of the `lsst-dm/milestones <https://github.com/lsst-dm/milestones>`_ repository, version `0b5c4af9 <https://github.com/lsst-dm/milestones/commit/0b5c4af9195bc035397d971a862444503779799d>`_, dated 2024-03-23.
This corresponds to the status recorded in the project controls system for January 2024. This compares to December 2023.
This document was generated based on the contents of the `lsst-dm/milestones <https://github.com/lsst-dm/milestones>`_ repository, version `47919931 <https://github.com/lsst-dm/milestones/commit/4791993188c03dfe73be73237d14a7d9f45f8869>`_, dated 2024-05-01.
This corresponds to the status recorded in the project controls system for March 2024. This compares to February 2024.

Top milestones
Key milestones
==============

.. list-table::
Expand All @@ -20,194 +20,142 @@ Top milestones
- Name
- Due
- Previously
* - EPOC285
- EPO Construction Finish
- 2022-09-30
- **Completed**
* - T&SC-0400-1730
- TMA Handoff to Rubin
- 2023-03-31
- **Completed**
* - CAMM8090
- COMP: Camera Pre-Ship Review at SLAC
- 2024-04-25
- 2024-03-26
* - SUMMIT-Oct24-160
- ComCam Reinstalled on TMA
- 2024-06-26
- 2024-06-17
* - T&SC-1100-0400
- 3-Mirror Optical System Ready for Testing
- 2024-07-05
- 2024-07-22
* - COMC-060200-20930
- Camera Ready for Full System AI&T
- 2024-10-08
- 2024-09-17
* - T&SC-0400-0950
- Dome Complete
- 2024-12-16
- 2024-12-16
* - SITCOM-122
- LSSTCam Ready for On Sky (First Photon)
- 2025-01-14
- 2025-02-19
* - LSST-1520
- System First Light with LSSTCam
- 2025-02-27
- 2025-04-04
* - LDM-503-17a
- Test report: Final Pipelines Delivery
- 2025-06-25
- 2025-07-31
* - COMC-0654-0430
- COMP: Science Validation Surveys Complete
- 2025-06-25
- 2025-07-31
* - SITCOM-130
- Operation Readiness Review Complete
- 2025-07-02
- 2025-08-07


A public HTML version for embedding is `here <./top_milestones.html>`_.

Supporting milestones
=====================

.. list-table::
:header-rows: 1

* - Code
- Name
- Due
- Previously
* - LDM-503-11a
- ComCam Ops Readiness
- 2020-12-31
- **Completed**
* - EPO-M6
- User Interfaces Complete
- 2022-09-30
- **Completed**
* - EPOC304
- Citizen Science Commissioning Project running via LSST infrastructure Complete
- 2022-09-30
- **Completed**
* - SITCOM-92
- Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope
- 2022-12-01
* - COMC-3010
- M1M3 Lift Test
- 2024-02-02
- **Completed**
* - LDM-503-13
- Ops rehearsal for data release processing #1
- 2023-02-28
* - COMC-3000
- TMA Final Testing Begins
- 2024-02-08
- **Completed**
* - DM-27734
- Completion of the Scheduler
- 2023-06-30
* - COMC-3030
- M1M3 Glass Lift Prep
- 2024-02-16
- **Completed**
* - SITCOM-127
- M2 coating decision
- 2023-10-01
* - COMC-3020
- Pathfinder Testing starts
- 2024-02-19
- **Completed**
* - LSST4820
- Love Contract Complete
- 2023-11-01
* - COMC-3040
- M1M3 Glass Installed
- 2024-03-20
- **Completed**
* - DM-35987
- OCS Available on Summit
- 2024-02-01
- 2024-01-02
* - DM-35989
- TCS Demonstrated
- 2024-02-01
- 2024-01-02
* - SITCOM-102
- TMA safe for transition to M1M3 glass mirror
- 2024-02-01
- 2024-01-02
* - SITCOM-97
- M1M3 cell+Surrogate Dynamic Testing on TMA done
- 2024-02-01
- 2024-02-05
* - SITCOM-105
- ComCam + PF re-Installed on TMA
- 2024-02-02
- 2024-01-03
* - COMC-3050
- TMA Final Testing Complete
- 2024-04-01
- 2024-03-01
* - COMC-3060
- M1M3 Coating Begins
- 2024-04-24
- 2024-04-10
* - COMC-3090
- LSSTCam Arrival Allowed
- 2024-04-24
- 2024-04-11
* - COMC-3110
- M2 Cell Removed from TMA
- 2024-05-07
- 2024-05-09
* - SUMMIT-2976
- LSSTCam Received @ Summit
- 2024-05-15
- 2024-04-23
* - SITCOM-104
- M2 Glass installed on Cell
- 2024-05-15
- 2024-05-23
* - DM-35988
- M2 Software demonstrated
- 2024-06-03
- 2024-05-02
* - SITCOM-109
- M1M3 Mirror Coating completed
- 2024-06-07
- 2024-06-24
* - T&SC-1100-0300
- M2 Installed on Telescope
- 2024-06-20
- 2024-06-11
* - SITCOM-110
- M1M3 installed on the TMA
- 2024-07-05
- 2024-07-22
* - SITCOM-125
- LSSTCam reverification complete
- 2024-10-08
- 2024-09-17
* - SITCOM-123
- LSSTCam Installed on TMA
- 2024-11-20
- 2025-01-29
* - New1135
- LSSTCam Cold
- 2025-01-07
- 2025-02-12
* - SUMMIT-3023
- COMP: TMA Refrigeration Tests Complete
- 2025-01-29
- 2025-01-29
* - New1110
- Full focal plane readout complete
- 2025-01-30
- 2025-03-07
* - New1165
- Telescope Aligned
- 2025-01-31
- 2025-03-10
* - DM-AP-17
- Solar System Processing pipeline (SSP) available.
- 2025-02-27
- 2025-04-04
* - SITCOM-116
- Initial Optical testing on TMA complete
- 2025-02-27
- 2025-04-04
* - SITCOM-121
- System First Light with LSSTCam
- 2025-02-27
- 2025-04-04
* - COMC-0140
- Start SV Data Collection
- 2025-04-04
- 2025-05-12
* - DM-AP-16
- Full integration of the Alert Production system within the operational environment.
- 2025-06-25
- 2025-07-31
* - LDM-503-16
- Ops rehearsal for data processing #3
- 2025-07-02
- 2025-08-07
- 2024-05-22
* - COMC-3070
- ComCam Removed from TMA
- 2024-05-29
- 2024-04-08
* - COMC-3080
- LSSTCam Pack and Transport
- 2024-05-29
- 2024-04-15
* - COMC-3120
- M2 Glass Installed
- 2024-06-19
- 2024-05-20
* - COMC-3130
- M2 Glass on TMA
- 2024-07-03
- 2024-07-16
* - COMC-3140
- ComCam Installed on TMA
- 2024-07-12
- 2024-07-25
* - COMC-3170
- LSSTCam Reverification Start
- 2024-07-19
- 2024-07-26
* - COMC-3150
- M1M3 Glass on TMA
- 2024-07-26
- 2024-07-12
* - COMC-3160
- ComCam First Photon
- 2024-07-29
- 2024-07-26
* - COMC-3180
- ComCam off Sky
- 2024-09-20
- 2024-09-19
* - COMC-3200
- LSSTCam Reverification End
- 2024-09-25
- 2024-10-02
* - COMC-3190
- ComCam off TMA
- 2024-09-27
- 2024-09-26
* - COMC-3210
- LSSTCam on Top End Assembly
- 2024-10-11
- 2024-10-16
* - COMC-3220
- LSSTCam L3 Checkout Done
- 2024-10-25
- 2024-10-30
* - COMC-3230
- LSSTCam on TMA
- 2024-11-11
- 2024-11-13
* - COMC-3240
- TMA Aligned
- 2024-11-18
- 2024-11-21
* - COMC-3250
- Rubin First Photon
- 2025-01-03
- 2025-01-08
* - COMC-3260
- TMA Pointing Models Complete
- 2025-01-22
- 2025-01-27
* - COMC-3270
- TMA AOS Ready
- 2025-02-18
- 2025-02-21
* - COMC-3280
- Rubin First Light
- 2025-03-26
- 2025-03-31
* - COMC-3290
- Rubin SV1 Start
- 2025-05-20
- 2025-05-23
* - COMC-3300
- Rubin SV2 Start
- 2025-05-20
- 2025-05-23
* - COMC-3310
- Rubin Eng Prep for OPS Start
- 2025-06-16
- 2025-06-19
* - COMC-3320
- Rubin Operations Readiness Review
- 2025-06-23
- 2025-06-26


A public HTML version for embedding is `here <./top_milestones.html>`_.