insulate garage north wall #88

Closed
16 of 17 tasks
msimerson opened this issue Aug 10, 2016 · 1 comment
Closed
16 of 17 tasks

insulate garage north wall #88

msimerson opened this issue Aug 10, 2016 · 1 comment

Comments

@msimerson
Copy link
Owner

msimerson commented Aug 10, 2016

part of #16

prep walls

  • strip walls to plywood
    • remove existing siding
    • remove / disconnect anything else attached to walls
  • strip siding from wall
  • remove windows
  • reframe window openings
    • oversize the rough opening:
      • +1/2" vertical for sloped sill (use siding material) to push water out
      • +1.5" for width of plywood extensions (3/4" all around)
  • spray foam fill all cracks and holes
  • tape plywood seams

install insulation

  • install z-channel flashing
  • install foam board, caulk all outer edges, tape all seams
  • install 2nd layer, joints offset, caulk all outer edges, tape all seams
  • cut out window holes
  • install bucks / plywood extensions to outside edge of insulation board
  • install furring strips (screw 24" o.c. to 1.5" stud penetration)
  • install insect screening / perfed J-channel / etc. to keep 'em out of rain screen
@msimerson msimerson mentioned this issue Aug 10, 2016
18 tasks
@msimerson msimerson changed the title Insulate garage N. wall insulate and side garage north wall Aug 10, 2016
@msimerson msimerson added this to the Superinsulate the house milestone Aug 10, 2016
@msimerson msimerson self-assigned this Aug 10, 2016
@msimerson msimerson mentioned this issue Aug 10, 2016
9 tasks
@msimerson msimerson changed the title insulate and side garage north wall insulate garage north wall Aug 11, 2016
@msimerson
Copy link
Owner Author

msimerson commented Aug 11, 2016

start removing siding (Jul 19)
jul 19

siding removed (Jul 19)
jul 19-2

insulation started (Jul 28)
jul 28

insulation progress (Jul 31)
jul 31

almost done (Aug 02)
aug 02

window cutout (Aug 03)