Project Evaluation and Review Technique

PERT is a method of analyzing the tasks involved in completing a given project, especially the time needed to complete each task, and to identify the minimum time needed to complete the total project

This code is for a Pert system using Python OOP, demonstrating the essential facts and functionalities of managing project.

Visualizing critical path schedule:

image

The program (or project) evaluation and review technique (PERT) is a statistical tool used in project management, which was designed to analyze and represent the tasks involved in completing a given project.

Critical Path Method graph

Critical Path Analysis is commonly used with all forms of projects, including construction, aerospace and defense, software development, research projects, product development, engineering, and plant maintenance, among others. Any project with interdependent activities can apply this method of mathematical analysis

Components:

The essential technique for using CPM is to construct a model of the project that includes the following:

  1. A list of all activities required to complete the project (typically categorized within a work breakdown structure),
  2. The time (duration) that each activity will take to complete,
  3. The dependencies between the activities and,
  4. Logical end points such as milestones or deliverable items.