Skip to content

Commit

Permalink
Merge pull request #66 from onflow/supun/emulator-migration
Browse files Browse the repository at this point in the history
Add emulator state migration guide
  • Loading branch information
SupunS committed Mar 13, 2024
2 parents e120667 + 253f5de commit fa8d854
Showing 1 changed file with 80 additions and 0 deletions.
80 changes: 80 additions & 0 deletions docs/cadence_migration_guide/emulator-state-migration-guide.mdx
Original file line number Diff line number Diff line change
@@ -0,0 +1,80 @@
---
title: Migrating Emulator state to Cadence 1.0
description: How to locally test storage migration and staged contract upgrades on Emulator
sidebar_position: 7
---

Flow CLI provides a command `flow migrate state` to migrate your local emulator
state to Cadence 1.0, and to deploy upgraded contracts to the emulator.
This is useful for locally testing the staged contract upgrades, and to see how the
new network and the upgraded contracts would behave with the migrated data.

## Migration Guide

To test the migration, first you would need an emulator state, created with an emulator/CLI release
that uses a pre-1.0 Cadence version.

### Getting the old state

It is recommended to use the latest pre-1.0 CLI version (e.g: `v1.14.*`) for creating the old state.
This is because the emulator shipped with older CLI versions may not include some of the system contracts
(e.g: `RandomBeaconHistory` contract) that are included by default in the newer versions of the emulator/CLI.
Such contracts are required for the migration.

**To get an emulator state with Flow CLI `1.14.0`:**

- Start the emulator with the `--persist` flag.
```shell
flow emulator --persist
```

- Deploy the pre-1.0 project/contracts to the emulator
- Run transactions if there are any.
- Stop the emulator (Ctrl-C on *nix platforms, and Ctrl-Break or Ctrl-Pause on Windows).
**It is important to make sure the emulator is stopped before taking the snapshot,
so that any pending in-memory data would be written to the persisted state properly.**
- Locate the persisted state `./flowdb/emulator.sqlite` file, from the project root.

### Migrating the state

Download and install the latest CLI, that runs Cadence 1.0.

- Run `flow-c1 migrate` against the previously created state.

- The state file (`emulator.sqlite`) can be provided using the `--db-path` flag.

- If there are any contracts that also need to be upgraded, those can be specified using the `--contracts` flag.
**Note that, the paths to these updated contracts and their deployed addresses must be specified in the `flow.json` file.**
For example, assuming the contract was deployed in the `test` account in the emulator,
and assuming the updated contract is in the `./updated_test_contract.cdc` file, the `flow.json` should include:
```json
{
"contracts": {
"Test": "./updated_test_contract.cdc"
},
"deployments": {
"emulator": {
"test": [
"Test"
]
}
}
}
```

- The migration will produce a report consisting of the migration status.
This can be enabled by setting the `--save-report` flag.

A sample `migrate` command would look like:

```shell
flow-c1 migrate state --db-path=/path/to/emulator.sqlite --save-report=./reports --contracts="Test"
```

### Testing the migrated state

Once the migration completes successfully, the emulator can be started with the migrated state.
For that, ensure the emulator is started again using the new CLI version (that runs Cadence 1.0),
with the `--persist` flag.
Now the emulator should be up and running using the migrated state and the updated contracts.
Run any transactions to verify the correctness of the existing data.

0 comments on commit fa8d854