Add quiz from original slides #39
Browse files Browse the repository at this point in the history
  • Loading branch information
pintergreg committed Feb 2, 2022
1 parent 4fc6f9c commit ceba38b
Showing 1 changed file with 119 additions and 0 deletions.
119 changes: 119 additions & 0 deletions src/lectures/agile_scrum_kanban.md
Original file line number Diff line number Diff line change
Expand Up @@ -402,3 +402,122 @@ Akkor tud egy csapat „cross-functional” lenni, ha minden tagja kellőképpen
UNUSED
https://agilepearls.wordpress.com/category/agile-sw-methodology/
-->

<!-- slide -->
<!-- .slide: data-visibility="hidden" -->
## Quiz

<pre>
<div class="quizdown">
---
shuffleQuestions: true
shuffleAnswers: true
---

### Scrum does not have a role called "project manager".

1. [x] True
1. [ ] False

### Which statement best describes a Product Owner's responsibility?

1. [x] Optimizing the value of the work the Development Team does.
1. [ ] Directing the Development Team.
1. [ ] Managing the project and ensuring that the work meets the commitments to the stakeholders.
1. [ ] Keeping stakeholders at bay. 

### The Development Team should have all the skills needed to?

1. [ ] Complete the project as estimated when the date and cost are committed to the Product Owner.
1. [ ] Do all of the development work, except for specialized testing that requires additional tools and environments.
1. [x] Turn the Product Backlog items it selects into an increment of potentially releasable product functionality.

### What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity?

- [x] By facilitating Development Team decisions.
- [x] By removing impediments that hinder the Development Team.
- [ ] By starting and ending the meetings at the proper time.
- [ ] By keeping high value features high in the Product Backlog.

### What is the main reason for the Scrum Master to be at the Daily Scrum?

1. [ ] To make sure every team member answers the three questions.
1. [x] He or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum.
1. [ ] To write down any changes to the Sprint Backlog, including adding new items, and tracking  progress on the burn-down.
1. [ ] To gather status and progress information to report to management.

### The purpose of a Sprint is to produce a done increment of working product.

1. [x] True
1. [ ] False

### The length of a Sprint should be:

1. [ ] Short enough to keep the business risk acceptable to the Product Owner.
1. [ ] Short enough to be able to synchronize the development work with other business events.
1. [ ] No more than one calendar month.
1. [x] All of these answers are correct.

### The time-box for a Daily Scrum is?

1. [ ] The same time of day every day.
1. [ ] Two minutes per person.
1. [ ] 4 hours.
1. [x] 15 minutes.
1. [ ] 15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter.

### Who is required to attend the Daily Scrum?

1. [x] The Development Team.
1. [ ] The Scrum team.
1. [ ] The Development Team and Scrum Master.
1. [ ] The Development Team and Product Owner.
1. [ ] The Scrum Master and Product Owner.

### Which statement best describes Scrum?

1. [ ] A complete methodology that defines how to develop software.
1. [ ] A cookbook that defines best practices for software development.
1. [x] A framework within which complex products in complex environments are developed.
1. [ ] A defined and predictive process that conforms to the principles of Scientific Management.

### Which of the below are roles on a Scrum Team?

- [x] Development Team
- [ ] Users
- [ ] Customers
- [x] Product Owner
- [x] Scrum Master

### The Product Backlog is ordered by:

1. [ ] Size, where small items are at the top and large items are at the bottom.
1. [ ] Risk, where safer items are at the top, and riskier items are at the bottom
1. [ ] Least valuable items at the top to most valuable at the bottom.
1. [ ] Items are randomly arranged.
1. [x] Whatever is deemed most appropriate by the Product Owner.

### When might a Sprint be abnormally terminated?

1. [ ] When it becomes clear that not everything will be finished by the end of the Sprint.
1. [ ] When the Development Team feels that the work is too hard.
1. [ ] When the sales department has an important new opportunity.
1. [x] When the Sprint Goal becomes obsolete.

### Who has the final say on the order of the Product Backlog?

1. [ ] The Stakeholders
1. [ ] The Development Team
1. [ ] The Scrum Master
1. [x] The Product Owner
1. [ ] The CEO

### The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress. What should the Development Team do?

1. [ ] Add the item to the current Sprint without any adjustments.
1. [ ] Add the item to the current Sprint and drop an item of equal size.
1. [ ] Add the item to the next Sprint.
1. [x] Inform the Product Owner so he/she can work with the CEO.

</div>
</pre>