{{site.data.alerts.important}}
- {{site.twoPeopleOrLift}}
- If you install the {{site.q1uag1}} 245 TB node type, ensure that the node cabling has sufficient slack to allow you to reach the internal storage bays.
For nodes without drives, follow the Tool-Less Friction Rail Kit Installation Guide in the ASUS documentation.
For nodes with drives in internal storage bays, you can purchase the optional 1.2m Half Extension Ball Bearing Type Rail Kit together with the Cable Management Arm. These two items replace the Tool-Less Friction Rail Kit.
{% include note.html content="To permit access to the internal storage bays, leave clearance at the top of the chassis." %}
Perform the steps for inserting the chassis in reverse order.