Assuming development begins mid-March, we are targeting an ultimate Mainnet launch of October 2018.
- The work will be broken into four Milestones for a total of ~26 weeks of work.
- Full test coverage will be maintained through milestone completion.
- At the end of each milestone, the app will be redeployed to testnet with new features or enhancements.
- Initialize Planning App
- Github Integration
- Off-Chain Bulk Bounties
- Range Voting
- Issue Curation
- Payout Engine
- Testnet Launch
- Fixed Payout
- Dynamic Payout
- Rewards Engine
- Testnet Launch
- Consensus Voting
- Planning Poker (On-Chain Bulk Bounties)
- Testnet Launch
- Finalize Planning App
- Comprehensive Scenario Testing
- Mainnet launch of all work
- Enhancement Plan for Decentralized Git Cross-Compatibility (Document)
The following stretch goals will be implemented if we accomplish the primary features before 26 weeks:
- Project Proposal
- Reputation Marketplace
- Integrating DAI into Aragon