Tasks & Critical Path

tomerye11 edited this page May 19, 2024 · 1 revision

Critical Path Diagram and Project Task Breakdown:

  • A – Design and Development of the Registration Page (2 weeks)
  • B – Database Development (2 weeks)
  • C – Development of Automatic Filling of National Insurance Form (2 weeks)
  • D – Development of Email Sending System (2 weeks)
  • E – Development of Registration Page Management System (1 week)
  • F – Integration Testing and Full System Testing (2 weeks)
  • G – Feedback and Final Corrections (2 weeks)

Note : After each stage, integration for that stage is performed.

Activity Table:

Activity Immediate Predecessor(s) Duration (weeks)
A --- 2
B --- 2
C B 2
D B 2
E A, B 1
F E, C, D 2
G F 2

Diagram:

critical path