- Figure out on how to distribute the work for project part 3 haly-way checkpoint.
- The Backlog file is completed with a story size and risk level evaluation on each story.
- The work distribution is decided and recorded in this meeting log.
- Initialize the project: shariatz
- DB set up: dennea
- JUnit set up: yliu30
- US 01.01.01: villarre & shariatz
- US 01.02.01: villarre
- US 01.03.01: prabhnoo
- US 01.04.01: jgerun
- US 01.05.01: shariatz
- US 01.06.01: dennea & jgerun & yliu30
- US 02.01.01: dennea & villarre
- US 02.02.01: prabhnoo & yliu30
- US 02.03.01: yliu30
- US 02.04.01: jgerun
- US 02.05.01: dennea & jgerun
- US 02.06.01: yliu30
- US 02.07.01: dennea & villarre
- US 02.08.01: shariatz & prabhnoo
- Team members who are responsible for a whole part of user stories (e.g. Ingredients) should work closely together, so that each of those user stories would have greater consistency.