TASKS AND DEPENDENCIES

Boaz Kimambo edited this page Jan 10, 2021 · 2 revisions

TASKS AND DEPENDECIES:

  • T1: Project Proposal (2)
  • T2: Project Planning (2)
  • T3: Functional Requirements Analysis (1)
  • T4: Non-functional Requirements Analysis (1)
  • T5: Database Design (2)
  • T6: Architectural Design (2)
  • T7: Conceptual Design (2)
  • T8: Business Process Diagram Design (1)
  • T9: Database Implementation (7)
  • T10: Architectural Implementation (7)
  • T11: Backend Implementation (15)
  • T12: Unit Testing (2)
  • T13: System Testing (3)
  • T14: User Manual Deployment (2)
  • T15: Maintenance Plan Layout (1)
  • ** In brackets is the allocated time in days for the specific task.
  • The dependencies and critical path for the project have been added manually in a separate file in the repo. The description for the image is as follows:
  • The tasks in red circle are the dependencies for their predecessors.
  • The red arrows depict the critical path for the project with clear outline of the number of days the project is expected to take.