  • Working through issues in the model setup
  • Discussed visualizer comparisons of survey to model
  • Generally a good match is coming together
  • Issues that still need follow-up:
    • Walk / bike mode share too high
    • Survey tour generation rates
    • Check trip time-of-days
  • Andrew keep working on fixes
  • Then work on documentation, updating GitHub, and doing a full scale run to update the visualizer
  • MetCouncil still working on batch file setup to share with us
  • We'll figure out the training plan once we get the obvious bugs out (...i.e. the list above)
  • We've spent about 1/3 of the project budget through September