Dear all, in the analysis of geotechnical problems, often I have to simulate an excavation or construction process. Due to non linearity, either processes need to be spread over a number of analysis increments. A typical approach to the excavation problem involves:
For construction:
I've found that elements can be removed or added to the analysis domain through e.g.: Best, |
Beta Was this translation helpful? Give feedback.
Replies: 2 comments 4 replies
-
Hello While the process of changing an element from a subdomain to another is abrupt (as soon as the threshhold is passed), you can create BCs/material properties that depend continuously on the threshold or another variable to ramp the other quantities slower. I would use something like max(0, variable - threshold value) / (max_variable_value - threshold value) as a multiplier Guillaume |
Beta Was this translation helpful? Give feedback.
-
Hello, can you tell me the use 'CoupledVarThresholdElementSubdomainModifier' can simulate filling process? If possible, could you please provide more detailed instructions? It would be nice to have an example. Thank you for your help. |
Beta Was this translation helpful? Give feedback.
Hello
While the process of changing an element from a subdomain to another is abrupt (as soon as the threshhold is passed), you can create BCs/material properties that depend continuously on the threshold or another variable to ramp the other quantities slower.
I would use something like max(0, variable - threshold value) / (max_variable_value - threshold value) as a multiplier
Guillaume