Hello

While the process of changing an element from a subdomain to another is abrupt (as soon as the threshhold is passed), you can create BCs/material properties that depend continuously on the threshold or another variable to ramp the other quantities slower.

I would use something like max(0, variable - threshold value) / (max_variable_value - threshold value) as a multiplier

Guillaume

Replies: 2 comments 4 replies