The application will be implemented in 4 iterations. Each iteration has a duration of one week.
At the start of each iteration, the project plan and project requirements are reviewed and updated as necessary, and an iteration plan is created. A task board and issues are used to record and track work and defects.
Iteration | Features |
---|---|
1 | Display a list of poll questions. |
Each poll question is linked to a page that displays the question and a list of choices. | |
Visitor can choose a poll question and vote on it. His/her vote is counted toward the total. | |
Visitor can see the total votes for each choice on a poll question after voting. | |
Every poll has a publication date (start date) and is only visible on or after that date. | |
The poll questions and responses are saved in a database. | |
Polls can be added or changed using the admin interface. |