Skip to content

This is an R program that takes an activity table whether it is a CPM or a PERT and and proccess it to find the critical path (along with some other calculations in the PERT method )

License

Notifications You must be signed in to change notification settings

tarek-hassan-FE/PERT-CPM-METHODS

 
 

Repository files navigation

Introduction

This is an R program that takes an activity table whether it is a CPM or a PERT and and proccess it to find the critical path (along with some other calculations in the PERT method )

The Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM) were developed by management scientists to help organizations with planning, scheduling and controlling large projects,such as building a new hospital orlaunching a new product.

large projects has series of interdependent activities that take time to complete,require funds and resources, such as time andlabor.

Interdependence means that activities follow a given sequence orprecedence relationship -some activities cannot start until others are completed.

Steps :

  • Step 1. Identify theactivities
  • Step 2. Determine activity relationships (immediate predecessors of eachactivity)
  • Step 3. Estimate activity completion times andcosts
  • Step 4. Construct an activitynetwork
  • Step 5. Execute a forward pass to determine earliest start and earliest finish times for each activity, and project completion time
  • Step 6. Execute a backward pass to determine latest start and latest finish times for each activity
  • Step 7. Identify activity slack (length of time an activity can be delayed without delaying the project completiontime)
  • Step 8. Find the activities with zero slack; these are critical activities and make up at least one critical path
  • Step 9. Use information from Steps 5 -8 to develop the activity schedule for the project.
  • Step 10. Find project completion time variance and conduct probability analysis, suchas the probability of meeting a customer target completion time, under the condition of uncertainty in activity times.
  • Step 11. Consider time-cost tradeoffs
  • Step 10. Implement, monitor and control the project.

1- Critical Path Method

The critical path method, or critical path analysis, is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique.

Steps :

  • takes an activity table with each activity's titel, immediate predecessor(s) and time and stores it into a graph

  • using a modified Breadth First Search algorithm to traverse the graph to find the forward and backward path

  • in the forward path it calculates the ES (Early Start time) and EF (Early Finish time ) of each activity

  • in the backward path it calculates the LS (Late Start time ) and LF (Late Finish time ) of each activity

  • calculate the slack value of each activity

    ES (Early Start Time) = maximum value of "EF" for all the activities it depends on
    EF (Early Finish Time) = ES + Activity time
    LF (Late Finish Time) = minimum value of "LS" for all the activites that depends on this activity LS (Late Start Time ) = LF - Activity time
    S (Slack Value) = LS - ES of each activity, if it's zero then this activity is in the critical path

  • draws a plot showing the graph, the attributes for each node and the critical path (green nodes),

Here is Some Sample Tests And It's Output

Activity Title Immediate Predecessors Activity Time
A Identify market need - 3
B Conduct R&D A 60
C Design packaging A 5
D Select product size A 15
E Conduct product test B 6
F Install production process D 40
G Perform market analysis C E 10
H Production startup F 7
I Make modifications G 6
J Market product H I 12

fig1

fig1

   


   
Activity Title Immediate Predecessor Activity Time
A High-level analysis - 7
B Selection of hardware platform A 7
C Installation and commissioning of hardware B 14
D Detailed analysis of core modules A 14
E Detailed analysis of supporting modules D 14
F Programming of core modules D 14
G Programming of supporting modules E 21
H Quality assurance of core modules F 7
I Quality assurance of supporting modules G 7
J Core module training C H 1
K Development and QA of accounting reporting E 7
L Development and QA of management reporting E 7
M Development of Management Information System L 7
N Detailed training I J K M 7

fig1

fig1

   


   
Activity Title Immeediate Predecessors Activity Time
A "TEST" - 2
B "TSET" A 4
C "TEST" B 3
D "TEST" B 2
E "TEST" C D 10
F "TEST" B 4

fig1

fig1

   


   
Activity Title Immediate Predecessors Activity Time
A "TEST" - 3
B "TEST" A 60
C "TEST" A 5
D "TEST" A 15
E "TEST" B 6
F "TEST" D 40
G "TEST" C E 10
H "TEST" F 7

fig1

fig1






2- PERT method

PERT is a scheduling technique that was specifically designed by the Navy in 1958for projects with uncertain activitytimes.

Steps :

  • Takes an activities table as follow (Activity - Title - Immediate Predecessor - Optimistic Time - Most probable Time - Pessimistic Time )
  • Finds the Expected Time for each activity by : expected_time(a) = ( Optimistic Time + 4 * Most probable Time + Pessimistic Time ) / 6
  • Finds the variance of each activity by : variance(a) = (Pessimistic Time - Optimistic Time ) ^ 2 / 36
  • sends the modified table to CPM function to find the critical path
  • Find mean which is the sum of Expected Times of critical path activities
  • Finds the total variance which is the sum of Variance o critical path activities
  • Finds the standard deviation which is the square root of variance
  • Finds the probabilty to finish the project on a specific Time

Here is Some Sample Tests And It's Output

Activity Immediate Prodecessor Optimistic Time Most probable Time Pessimistic Time
A - 6 9 12
B A 3 4 11
C A 2 5 14
D B-C 4 6 8
E C 1 1.5 5
F E 5 6 7
G D 7 8 15
H B 1 2 3

pert1 pert2

|              Task     |    ans     |
| -------------------   | ---------- |
|              Variance | 7.22222222 |
|    Standard Deviation | 2.68741925 |
| Propability on 26 day | 4.9%       |

About

This is an R program that takes an activity table whether it is a CPM or a PERT and and proccess it to find the critical path (along with some other calculations in the PERT method )

Topics

Resources

License

Stars

Watchers

Forks

Releases

No releases published

Packages

 
 
 

Languages

  • R 100.0%