Skip to content
New issue

Have a question about this project? Sign up for a free GitHub account to open an issue and contact its maintainers and the community.

By clicking “Sign up for GitHub”, you agree to our terms of service and privacy statement. We’ll occasionally send you account related emails.

Already on GitHub? Sign in to your account

Set up rack and cabling for new switch #11

Closed
Tracked by #9
1Copenut opened this issue Jan 27, 2022 · 1 comment
Closed
Tracked by #9

Set up rack and cabling for new switch #11

1Copenut opened this issue Jan 27, 2022 · 1 comment
Labels
Milestone

Comments

@1Copenut
Copy link
Owner

Description

Punch down cable endpoints, build the rack, start provisioning the switch, running cable

@1Copenut 1Copenut mentioned this issue Jan 27, 2022
6 tasks
@1Copenut 1Copenut added this to the Rack Up milestone Feb 26, 2022
@1Copenut
Copy link
Owner Author

Finished this last weekend. All cables are punched down for the first phase and tested.